DAF Pretreatment for an Overloaded Truck-Stop Lagoon

Delivered DAF treatment upstream of an overloaded truck-stop lagoon, with automatic dosing and the existing lagoon retained.

Project Background

The client needed pretreatment for an overloaded food-service wastewater lagoon that was failing discharge tests and being tankered off site daily. The client-supplied design basis included meal-period peaking, sub-zero winters, no influent analysis, and a requirement to retain the existing lagoon. Capacity: ~40 m³/d.

Our Solution

We delivered a DAF unit with automatic coagulant and flocculant dosing inside heated space, with freeze protection on external lines. The physical-chemical process removes FOG and suspended solids before the existing lagoon, allowing the lagoon to remain in service. Equipment, installation, commissioning, performance verification, training, handover, and after-sales support were completed.

Process Train

  1. 1Grease interception
  2. 2equalisation
  3. 3DAF with automatic coagulant and flocculant dosing
  4. 4existing lagoon
  5. 5discharge

Read the full engineering record →

Ref. D-040. Client identity is withheld under our client-confidentiality policy. Capacity is shown as a capacity class (design value rounded up to the next 5 at its second significant digit).

How We Deliver

Projects of this type are delivered in the nine stages below. Installation, commissioning and other on-site stages follow each contract's scope. Every stage within our scope produces a written record that we keep on file.

  1. 1 Design basis confirmationAverage and peak flow, influent or gas data, discharge or reuse target Record producedDesign basis sheet
  2. 2 Process & mechanical designProcess calculations, equipment selection, layout and piping Record producedCalculation book, P&ID, general arrangement
  3. 3 Manufacturing & quality controlMaterial and in-process inspection of the main equipment Record producedMaterial & QC records
  4. 4 Factory acceptance test (FAT)Trial run against the design parameters before dispatch Record producedFAT record
  5. 5 Packing & dispatchPacked, marked and shipped against the equipment list Record producedPacking list
  6. 6 Installation or supervisionPer contract scope Record producedInstallation record
  7. 7 CommissioningStart-up, parameter tuning and interlocks Record producedCommissioning log
  8. 8 Performance verificationEffluent or emission checked against the design basis Record producedPerformance test record
  9. 9 Training, handover & after-salesOperator training, document handover, after-sales support Record producedO&M manual, training record

Planning a similar project? Start with these six parameters

  1. FlowDaily average and peak (m³/day and m³/h)
  2. Influent qualityCOD, BOD₅, TSS, pH and anything unusual
  3. Discharge targetThe standard you must meet, or the reuse purpose
  4. Operating hoursContinuous or batch; seasonal changes
  5. Site & civil scopeFootprint, power supply, who builds the tanks
  6. Project stageBudgeting, tender, or ready to order

Send your parameters — initial process recommendation within 24 hours

Frequently Asked Questions

This project is listed in the ~40 m³/d capacity class: the design value rounded up to the next 5 at its second significant digit. Exact design values are not published.
The process train was: Grease interception → equalisation → DAF with automatic coagulant and flocculant dosing → existing lagoon → discharge.
Yes. Send us your daily and peak flow, influent quality, discharge or reuse target, operating hours and site constraints, and our engineers will reply with an initial process recommendation within 24 hours.

Planning a similar project?

Share your flow, influent quality and discharge target — our engineers respond within 24 hours.

AI Growth
Contact
Contact Us
Call Us
+86-181-0655-2851
Email Us Get a Quote Contact Us