8 m³/d hospital wastewater treatment system – Senegal

Proposed package MBR treatment for clinic wastewater, subject to client flow, discharge route and permit confirmation.

Project Background

The client-supplied design basis is 8 m³/d for a new outpatient and inpatient medical facility. Client-estimated wastewater characteristics are BOD₅ 250–400 mg/L, COD 500–800 mg/L and TSS 200–350 mg/L. The proposed treatment targets BOD₅ below 30 mg/L, COD below 90 mg/L and TSS below 30 mg/L, subject to testing, design confirmation and applicable approval.

Our Solution

Provide a complete package treatment system using a rotary screen for debris removal, equalisation and flow diversion, an anaerobic hydrolysis and anoxic stage, aerobic biological treatment with internal recycle, and ultrafiltration membrane separation. Apply chemical dosing only after confirming the incoming wastewater characteristics and treatment objectives. Chlorine dioxide provides final disinfection before the selected discharge or reuse route. Route separated solids to a compact thickening and plate-and-frame dewatering arrangement, then sealed storage pending authorised disposal. Keep laboratory, dialysis and surgical cleaning wastes outside this package until their independent neutralisation and responsibility boundaries are confirmed. Final process selection, sizing, hydraulic design, electrical provisions and permit compliance will be confirmed after the missing flow, quality, site and discharge information is received.

What We Asked First

Please confirm the peak hourly flow and drainage period, final discharge route, applicable permit and microbiological requirements, electrical supply and available power, site dimensions, inlet and outlet levels, and the boundary for separately collected chemical, dialysis and cleaning wastes.

Proposed Process Train

  1. 1Rotary mechanical bar screen
  2. 2equalisation and flow-diversion tank
  3. 3fine screen and automatic chemical dosing
  4. 4anaerobic hydrolysis and anoxic bioreactor
  5. 5aerobic biological stage and internal recycle
  6. 6membrane separation and permeate collection
  7. 7chlorine dioxide disinfection
  8. 8gravity sludge thickening and plate-and-frame dewatering
  9. 9sealed sludge storage and authorised off-site disposal

For Similar Projects

Prepare current wastewater sampling, peak-flow calculations, drainage schedules, discharge and reuse plans, utility details, site survey information, permit requirements, and a clear scope boundary for segregated clinical waste streams.

Ref. A-023. Client identity is withheld under our client-confidentiality policy. Capacity is shown as a capacity class (design value rounded up to the next 5 at its second significant digit).

How We Deliver

Projects of this type are delivered in the nine stages below. Installation, commissioning and other on-site stages follow each contract's scope. Every stage within our scope produces a written record that we keep on file.

  1. 1 Design basis confirmationAverage and peak flow, influent or gas data, discharge or reuse target Record producedDesign basis sheet
  2. 2 Process & mechanical designProcess calculations, equipment selection, layout and piping Record producedCalculation book, P&ID, general arrangement
  3. 3 Manufacturing & quality controlMaterial and in-process inspection of the main equipment Record producedMaterial & QC records
  4. 4 Factory acceptance test (FAT)Trial run against the design parameters before dispatch Record producedFAT record
  5. 5 Packing & dispatchPacked, marked and shipped against the equipment list Record producedPacking list
  6. 6 Installation or supervisionPer contract scope Record producedInstallation record
  7. 7 CommissioningStart-up, parameter tuning and interlocks Record producedCommissioning log
  8. 8 Performance verificationEffluent or emission checked against the design basis Record producedPerformance test record
  9. 9 Training, handover & after-salesOperator training, document handover, after-sales support Record producedO&M manual, training record

Planning a similar project? Start with these six parameters

  1. FlowDaily average and peak (m³/day and m³/h)
  2. Influent qualityCOD, BOD₅, TSS, pH and anything unusual
  3. Discharge targetThe standard you must meet, or the reuse purpose
  4. Operating hoursContinuous or batch; seasonal changes
  5. Site & civil scopeFootprint, power supply, who builds the tanks
  6. Project stageBudgeting, tender, or ready to order

Send your parameters — initial process recommendation within 24 hours

Frequently Asked Questions

This project is listed in the 8 m³/d capacity class: the design value rounded up to the next 5 at its second significant digit. Exact design values are not published.
The process train under assessment is: Rotary mechanical bar screen → equalisation and flow-diversion tank → fine screen and automatic chemical dosing → anaerobic hydrolysis and anoxic bioreactor → aerobic biological stage and internal recycle → membrane separation and permeate collection → chlorine dioxide disinfection → gravity sludge thickening and plate-and-frame dewatering → sealed sludge storage and authorised off-site disposal.
Yes. Send us your daily and peak flow, influent quality, discharge or reuse target, operating hours and site constraints, and our engineers will reply with an initial process recommendation within 24 hours.

Planning a similar project?

Share your flow, influent quality and discharge target — our engineers respond within 24 hours.

AI Growth
Contact
Contact Us
Call Us
+86-181-0655-2851
Email Us Get a Quote Contact Us