Hammanskraal’s long-running drinking-water crisis remained unresolved as coalition negotiations after the 7 November 2026 Tshwane council election put pressure on Mayor Nasiphi Moya’s programme of repairs and improved services allAfrica.com. The report said residents had waited more than 20 years for clean drinking water, while the failing Rooiwal wastewater treatment plant remained a central concern allAfrica.com.
KEY TAKEAWAYS
- Hammanskraal’s water problems date to 2004, when pollution linked to the failing Rooiwal wastewater treatment plant began affecting the Apies River and the dam supplying the area allAfrica.com.
- The national government, Magalies Water and Tshwane had started work on the R750-million Klipdrift project, whose first treatment unit began supplying selected communities in January 2025 allAfrica.com.
- Tshwane reported in April 2026 that two of four Klipdrift treatment units were complete, while repairs at Rooiwal continued allAfrica.com.
- Residents were still buying bottled water in February 2026 because lasting improvements had not reached them allAfrica.com.
WHAT HAPPENED
The report, published on 7 November 2026, said the coalition talks following the election raised the stakes for Moya because ActionSA wanted her to remain mayor for another five years but could not govern Tshwane alone allAfrica.com. ActionSA emerged with 48 of the council’s 214 seats, while the Democratic Alliance held 74 and the African National Congress 44; a party or coalition needed 108 seats for a majority allAfrica.com.
“We will be negotiating to ensure that Dr Nasiphi Moya gets five more years,” said ActionSA national chairperson Michael Beaumont allAfrica.com. Moya remained mayor while the parties negotiated, and the new council was required to elect the next mayor allAfrica.com.
Underneath the political transition, the engineering work remained incomplete. The national government, Magalies Water and Tshwane had already begun the R750-million Klipdrift project, with its first treatment unit supplying selected communities in January 2025 allAfrica.com. By April 2026, the city administration reported that two of four Klipdrift treatment units were complete, while repairs continued at Rooiwal allAfrica.com.
The report said remaining Klipdrift units still needed to start operating and Rooiwal needed lasting repairs allAfrica.com. Residents had not all experienced sustained improvement: Scrolla.Africa reported in February 2026 that Hammanskraal residents were still buying drinking water, with resident Melusi Sibeko describing spending part of his salary on bottled water allAfrica.com.
The wider crisis included a deadly cholera outbreak in May 2023, when emergency tankers supplied affected communities allAfrica.com. Although officials linked unsafe water to pollution from Rooiwal, investigators never confirmed the outbreak’s original source allAfrica.com.
SPECIFICATION READ
The Klipdrift project was designed to produce 12.5 million litres daily, equivalent to 12,500 m³/day allAfrica.com. The source did not report the design population equivalent, so a population-based capacity cannot be assigned from the available information.
For procurement purposes, the reported project bears directly on the wastewater-treatment and water-recovery stages needed to prevent treated effluent from compromising a downstream drinking-water source. A conventional train would normally be assessed from screening and primary treatment through biological treatment—such as A2O, MBBR, SBR or MBR—followed by tertiary treatment and disinfection; the source does not identify Klipdrift’s process configuration or specify whether DAF or ZLD was included allAfrica.com. Operators comparing treatment platforms can use A/O versus MBR: What a wastewater plant needs and A/O package plant versus MBR as technical reading.
If your plant serves a municipal community at 12,500 m³/day and must protect a downstream drinking-water supply from wastewater-process failures, this project shows the importance of completing commissioned capacity, maintaining reliable disinfection and proving sustained compliance rather than relying only on interim supply measures. The available report does not provide the influent BOD or COD, hydraulic peaks, discharge limits or required storage volume needed to specify an individual treatment train. Further information is also available through HydropureWater’s water purification product hub.
FAQ
What capacity has been reported for the Klipdrift project?
The first treatment unit began supplying selected communities in January 2025, and the project was designed to produce 12.5 million litres daily, or 12,500 m³/day allAfrica.com. Two of the four Klipdrift treatment units were reported complete in April 2026 allAfrica.com. The source did not provide the population served or the capacity of each completed unit.
What treatment stages need to be verified before equipment selection?
For a wastewater project protecting a drinking-water supply, the assessment should cover screening, primary treatment, biological treatment, tertiary treatment and disinfection, with additional processes selected only where the discharge and reuse requirements justify them allAfrica.com. The reported Klipdrift project did not identify its process configuration, while Rooiwal still required lasting repairs allAfrica.com.
What information is needed for an initial cost and delivery estimate?
The reported project value was R750 million, but the source did not provide an itemised equipment budget, procurement schedule or unit-by-unit delivery programme allAfrica.com. A reliable estimate would therefore require the treatment capacity allocated to each unit, design flow and peak demand, influent BOD and COD, required reuse quality, discharge criteria, site constraints and commissioning dates.
How should a supplier be selected for a plant of this scale?
The supplier should demonstrate that its proposed process can deliver the required flow and water quality, provide evidence for comparable municipal installations and specify commissioning and long-term support allAfrica.com. Klipdrift illustrates the delivery risk: although the first unit started supplying water in January 2025, two of four units were reported complete in April 2026 and the remaining units still needed to operate allAfrica.com.