Carlsberg Fredericia Water Recycling in the 2022 ESG Report

Who owns the Fredericia recycling project?

The Carlsberg Fredericia brewery in Denmark is the end-user site covered by a water-recycling plant commissioned in 2021, with Pantarein Water as OEM and DuPont DesaliTec CCRO units. The documented train uses aerobic and anaerobic biological treatment, an MBR, and CCRO filtration. DuPont Water Solutions reports a rated capacity of 83 m³/h (1,992 m³/d), while Carlsberg Group reported that the plant recycled 90% of process water in 2022. These are a design capacity and a company-reported operating result, not proof of daily throughput or an annual average.

Carlsberg Group is the operator and end user at Fredericia. DuPont Water Solutions identifies Pantarein Water as the OEM and states that Pantarein installed the Total Water Management facility in 2021 (DuPont Water Solutions, physical PDF p. 1). The historical sources do not identify HydropureWater as an OEM, installer or equipment supplier for this installation, so the case should be treated as a reference configuration rather than a claim about company experience.

That role distinction matters during procurement. Carlsberg defines the operating need, Pantarein is identified as the plant builder, and DuPont supplied the described CCRO units. A prospective buyer should still allocate biological design, pretreatment, membrane systems, pumping, controls, installation, commissioning, sludge handling and performance responsibility in its own contract rather than assuming those boundaries carried over from Fredericia.

The documented treatment train

A comparable quotation needs a unit-by-unit boundary because biological treatment, membrane separation and final purification solve different quality problems.

  1. Biological treatment: DuPont describes aerobic and anaerobic biological treatment as the first part of the train.
  2. MBR separation: The documented sequence continues through an MBR. For a prospective project, compare MBR membrane bioreactor systems against the required solids separation, reuse-water specification, peak loading, footprint and sludge-handling constraints.
  3. Final membrane treatment: DuPont DesaliTec CCRO units provide the final filtration stage described in the vendor case sheet. Evaluate industrial reverse osmosis systems only against verified salinity, hardness, organic rejection, recovery, pretreatment and concentrate-disposal requirements.
  4. Residual-stream handling: DuPont states that residual wastewater and sludge concentrate are sent to a nearby public wastewater treatment plant (DuPont Water Solutions, physical PDF p. 2). Full reuse must therefore not be assumed.

The published sequence does not specify aeration, sludge return, recirculation, prefiltration, antiscalant, storage or disinfection details. Require bidders to state which of these functions are included, where they sit in the flow diagram, and which downstream interface they affect.

Capacity, treatment capability and operating evidence

Do not combine the rated capacity, treatment capability and reported operating result into one performance claim: they describe different scopes and evidence levels.

Evidence item Scope What it establishes What it does not establish
Rated plant capacity: 83 m³/h (1,992 m³/d) DuPont Water Solutions customer story, physical PDF p. 1 Vendor-published design rating for the Fredericia recycling plant Measured daily throughput, annual utilization or operating availability
1,992 m³/d can be purified DuPont Water Solutions customer story, physical PDF p. 2 Stated treatment capability for process-water reuse A verified operating record or actual flow in every production campaign
90% of source wastewater treated to drinking water standards and recycled DuPont Water Solutions customer story, physical PDF p. 2 Vendor-described treatment capability and residual-stream split An independently verified site recovery rate
90% of all process water recycled Carlsberg Group ESG Report 2022, physical PDF p. 41 Company-reported operating result for one Fredericia site A Carlsberg Group-wide result, annual average or independent verification

For a comparable brewery, request measured hourly and daily flow records, operating availability, campaign-level production and water-quality data. The decisive question is not whether the quoted nameplate resembles Fredericia’s; it is whether the train performs at the buyer’s actual feed conditions and required product-water quality.

What the 1.4 hl/hl result does—and does not—prove

The 1.4 hl/hl figure is a selected-moment operating observation, not a full-year water-intensity benchmark.

Carlsberg Group reported 1.4 hl/hl for all beer production at Fredericia “at some instances” in 2022 (Carlsberg Group ESG Report 2022, physical PDF p. 41). The denominator covers all beer production at that brewery, but the stated circumstance is limited to selected moments during the reporting year. It does not support annualization, aggregation into a full-year average, or transfer to another brewery or Carlsberg site.

Use this result to identify what a strong water-reuse project may target, not to guarantee savings in a procurement model. Request hourly production, reuse-water flow, campaign boundaries and the operational events surrounding each observation. Those records are needed to distinguish genuine reuse from recycling credit, establish a defensible water balance and determine whether selected readings are representative. The broader considerations in industrial effluent and RO plant selection also apply: reuse-point demand and production variability must be resolved before equipment sizing.

Conditions that should determine the treatment route

Select each treatment step from verified influent and reuse requirements; the Fredericia sequence is a reference, not a universal recipe.

Discharge route or influent problem Governing rule or process option What data settles it
High biodegradable organic load Biological treatment is a candidate if the verified waste is biologically amenable and the required conversion can be achieved under site temperature and pH conditions. COD, BOD, temperature, pH, fats and oils, plus contaminants associated with brewery cleaning
Suspended solids and solids separation required before reuse Choose an MBR configuration around product-water quality, peak hydraulic and organic loading, footprint, membrane maintenance and sludge-management constraints. Influent suspended-solids profile, membrane filtrate specification, peak-flow data, operating-hour assumptions and sludge volume
Dissolved salts, hardness or organic rejection required Assess RO or CCRO against recovery, pretreatment, membrane replacement, concentrate handling and reuse-point quality limits. Salinity, hardness, organic characterization, recovery target, concentrate volume and receiving-site requirements
Residual wastewater and sludge concentrate remain Define an executable residual route rather than assuming complete reuse or omitting disposal costs and interfaces. Residual-stream volumes, sludge characteristics, disposal route, applicable receiving-site requirements and pretreatment needs

For high-strength streams, use the decision method in high-COD industrial wastewater treatment; for membrane concentration, establish the concentrate route before comparing recovery claims. The route should be accepted only when its complete mass and water balance remains operable under peak and campaign conditions.

Pre-quotation checklist and acceptance criteria

A defensible quotation separates inputs, guarantees and exclusions before the buyer treats any operating claim as contractual performance.

Quote line item Technical scope to specify Red flags to check before signing
Source-water and reuse-demand basis Hourly and daily wastewater flow, seasonal peaks, process-water reuse demand, storage requirement and reuse-point quality limits Nameplate capacity quoted without flow-duration data, production schedules or agreed design cases
Biological and MBR process design Influent characterization, reactor basis, aeration, sludge return, recirculation, solids separation, peak loading and footprint Undefined feed ranges, omitted pretreatment or an excluded sludge-handling scope
RO or CCRO system Feed-water limits, recovery, product-water guarantees, pretreatment, antiscalant, membrane schedule, cleaning and concentrate route Recovery or rejection stated without test conditions; concentrate disposal excluded from the price
Installation and commissioning Civil works, utilities, controls, installation, training, sampling, performance tests and handover documentation Equipment-only pricing presented as a complete operating installation
Performance guarantee Agreed feed conditions, test methods, sampling points, steady-state duration, off-specification treatment and remedy Guarantee tied only to “plant capacity,” with no water-quality or recovery test
Energy, consumables and sludge Measured or defined consumption targets, chemical basis, sludge balance, dewatering or disposal scope, maintenance and replacement obligations Exclusions that leave energy, chemicals or sludge handling with the site without a design allowance

Set acceptance criteria around measurable conditions, not the recycled percentage alone. Require the bidder to state sample locations, methods, test frequency, feed-water envelope, operating duration and treatment of failed tests. Apply the same discipline to sludge: request its generation basis, moisture or solids characteristics and disposal route, using industrial sludge dewatering design criteria where dewatering enters the scope.

Obtain these documents before requesting a comparable price: site flow and quality data, reuse-point specifications, residual-stream information, utilities and footprint constraints, proposed process flow and P&ID, equipment schedules, guarantee definitions, exclusions, commissioning tests, energy and consumable bases, sludge strategy, and the warranty and performance-remedy structure.

Frequently Asked Questions

Who supplied the Carlsberg Fredericia water-recycling installation?

DuPont Water Solutions identifies Pantarein Water as the OEM and says Pantarein installed the Total Water Management facility in 2021 using DuPont DesaliTec CCRO units (physical PDF p. 1). Carlsberg Group is the end user. The historical sources do not state that HydropureWater supplied the OEM, installation or equipment, so this project should not be presented as a HydropureWater installation.

Can the Fredericia capacity be used to size another brewery reuse plant?

No. The published 83 m³/h (1,992 m³/d) figure is a vendor-published design rating, not measured daily throughput (DuPont Water Solutions, physical PDF p. 1). Require the prospective site’s hourly and daily flow, seasonal peaks, feed quality, reuse demand, storage assumptions and product-water limits before selecting equipment capacity or recovery.

What measurements are needed for a defensible reuse acceptance test?

Agree the feed-water envelope, throughput, recovery, product-water parameters, sampling points, test methods, operating duration and permitted deviation before the test. Add direct flow and quality measurements rather than inferring performance from plant operation. Specify how off-specification results trigger investigation, retesting, correction or contractual remedies.

Should a brewery quotation include everything beyond the membrane equipment?

Specify what is included and who will supply, install and test anything excluded. Request separate pricing for biological design, pretreatment, membrane equipment, pumping, controls, installation, commissioning, sludge handling, energy, chemicals, monitoring and long-term guarantees. Compare bids using the same complete scope; an equipment-only quotation is not comparable with a turnkey biological–MBR–CCRO installation.

References

  1. Carlsberg Group ESG Report 2022 (PDF p. 41)
  2. DesaliTec™ Closed Circuit Reverse Osmosis (CCRO) System Helps Carlsberg Create a More Sustainable Water-efficient Brewery (PDF pp. 1, 2)

Related Articles

Industrial Effluent and RO Plant Selection for Mauritius
Nov 23, 2026

Industrial Effluent and RO Plant Selection for Mauritius

Choose an industrial effluent treatment and RO plant in Mauritius using a wastewater decision matri…

High-COD Industrial Wastewater Treatment in Benin: System Choice
Nov 23, 2026

High-COD Industrial Wastewater Treatment in Benin: System Choice

Choose a high-COD treatment train for Benin using wastewater tests, removal targets, equipment rout…

Sludge Press Equipment Design Criteria for Industrial Projects
Nov 23, 2026

Sludge Press Equipment Design Criteria for Industrial Projects

Define the sludge, performance, materials, operating and test criteria needed to select and specify…