Adding tertiary treatment to an existing wastewater plant is above all a scoping exercise: the owner who fixes, before tender, the target contaminant, the flow and load the existing works can pass in wet weather, the footprint and head available, the permitted bypass duration and the acceptance test gets bids that compete on solutions rather than on contingencies.
On 2026-11-26 Croatia's e-procurement bulletin EOJN published notice 2026/S F05-0002458 (CPV 45252100): an open procedure above EU thresholds for works to design and build the Ivanić-Grad wastewater treatment facility, buyer Vodoopskrba i odvodnja Zagrebačke županije d.o.o., estimated value 6,958,656.85 with no currency printed on the overview page, bids due 2027-01-04 12:00 (EOJN notice overview, basic procurement data). The buyer's project page lists, in its feasibility study, the Ivanić Grad plant with a third treatment stage, capacity 21,400 ES (population equivalents, PE), at the existing site, discharging to the Lonja river (buyer project page, feasibility study section).
The notice overview names neither the tertiary process nor the effluent limits, scope list, contract conditions or award criteria; the suggestions below are ours, not the buyer's requirements and not bid or legal advice.
Why an existing site changes the design
On a greenfield site the designer sets the hydraulic profile; on a retrofit, with footprint and levels already occupied, it is fixed. The last existing structure has a water level, the discharge into the Lonja river named on the project page will face a river level the designer cannot change, and the new stage must live within the head between them; if available head does not exceed the losses through the new units, valves and channels plus freeboard, a pumping station joins the scope. The Lonja river and the discharge requirements applied to it set the effluent quality, and with it the process.
- Hydraulic margin: the peak flow the existing secondary stage can pass before solids wash out; tertiary units are sized on peak flow, not the average.
- Tie-ins and bypass: every connection to a live plant needs a bypass route and a minimum flow that must still be treated; the new stage inherits the plant's controls and power.
- Future inflow: the same feasibility study also rebuilds sewers and adds collectors and pumping stations, so the catchment is not static; the notice overview does not say which of these works belong to this contract (buyer project page, feasibility study).
Choose the route by duty, not by habit
Three duties drive most third stages, and one plant may need all of them; general process descriptions sit in our tertiary treatment engineering guide and our disc filter buyer's guide.
| Duty | Typical process route | Condition that decides |
|---|---|---|
| Suspended solids and turbidity | Granular, cloth or disc filtration; membranes for a tighter output | Stable secondary effluent and head to spend |
| Deep phosphorus removal | Coagulant dosing, then settling, flotation or direct filtration | Room for a separation step; sludge capacity |
| Microbiological control | UV or chemical disinfection after filtration | Low turbidity and good transmittance upstream |
On a retrofit, a few relationships govern the trade-offs. Filtration area scales with peak flow divided by the chosen filtration velocity, so a unit sized on dry-weather flow backwashes almost continuously in a storm. Chemical demand scales with flow times dose, and the last fractions of phosphorus are the dearest: a very low target multiplies chemical use, sludge and cost because the residual phosphorus sits in solution, not in settleable particles. UV dose is intensity multiplied by exposure time, and both are wasted if the upstream stage leaves turbidity that shields organisms. Coagulation with settling is robust where there is land, dissolved air flotation (DAF) is compact and suits light flocs and algae, and direct filtration saves a stage but tolerates less variability.
Scope and responsibility in a design-build contract
Design-build moves detailed design to the contractor but leaves the owner responsible for defining the output, traced stage by stage so both sides know who holds each risk:
- Concept and main design: the route and the document set needed for permits, with the notice overview silent on who obtains them.
- Detailed design, construction and as-built drawings, with tie-in dates agreed around the plant's operating constraints.
- Commissioning, training, trial operation with verification of parameters, and rectification of defects after handover.
The owner's requirements fix inputs and outputs, not the process, so the contractor still designs within them; the inputs, none of which this notice discloses, are listed at the end of this article. For a related upgrade case, see our article on municipal wastewater plant upgrade with A²/O process enhancement.
Commissioning and acceptance logic
A workable acceptance clause answers four questions before construction starts:
- Verification conditions: the flow range, season and load during the test, and what happens if no storm occurs.
- Sampling and testing: sample points, frequency, composite or grab samples and an accredited laboratory.
- Performance parameters: guaranteed values, averaging period and permitted exceedances, none of which this notice overview discloses.
- Remedy order: re-test, then optimisation of dose and backwash, then modification, before contractual remedies apply.
Seasonal effects need explicit wording: low winter temperatures, summer algal growth and first-flush loads cannot all be observed in a short trial, so the contract should state how compliance is inferred for the rest of the year.
Equipment reference by duty
The table matches typical duties with equipment sold on this site; it is a reference for budgetary enquiries only, none of it selected for the Ivanić-Grad project.
| Duty | Where it fits a retrofit | Site equipment (reference only) |
|---|---|---|
| Separation after dosing | Light flocs or algae, limited land | DAF machine |
| Coagulant or phosphorus dosing | Before the separation or filtration step | Automatic chemical dosing system |
| Final solids and turbidity polishing | Barrier stage ahead of the outfall | Multi-media filter |
| Microbiological control at the outfall | After filtration, on low-turbidity effluent | UV sterilizer |
RFQ checklist before you ask for a quote
A supplier can size tertiary equipment quickly once it has the following:
- Effluent target: parameters, limits and the discharge permit they derive from.
- Existing plant: process, average and peak flow, current secondary effluent quality.
- Site: footprint, water levels, head, soil, power and tie-in points.
- Construction constraints: bypass duration, minimum flow to be treated, outage windows.
- Acceptance basis: test window, sampling plan and performance parameters.
Send these details through our request-a-quote page; HydropureWater supplies these equipment types for municipal and industrial wastewater plants, and our Croatia country page is the Croatia entry point on this site.
FAQ
What stage has the Ivanić-Grad project reached?
As of the notice published on 2026-11-26, the project is at open tender and bids are due on 2027-01-04 12:00. No award, contract signature or start of works has been announced; these depend on the buyer's later notices. The project page describes a feasibility study, not the state of construction.
What is hardest about adding tertiary treatment to a plant in operation?
Building and connecting the new stage without interrupting treatment. The hydraulic profile is fixed, the ground is occupied and every tie-in needs a bypass, so phasing and bypass conditions deserve as much space in the tender as the process.
What does the Ivanić-Grad notice not disclose?
The tertiary process, effluent limits, scope list, contract conditions, award criteria and the currency of the estimated value; bidders must take them from the full tender documents.