Sizing a vacuum evaporator for battery electrode wastewater comes down to three values: the daily volume, the peak flow and the buffer volume between them. While the streams are still being defined, our advice is to size the evaporator on the daily volume, size the buffer on the peak, and write every assumption into a design-assumption table that sampling and analysis can later confirm. Note that the public notice used as reference here lists an evaporator plant and a vacuum belt filter but does not specify the evaporator type, so vacuum evaporation is a route discussed here, not a description of that facility.
The reference is a first-hand record: the structured eForms award notice that the German announcement service oeffentlichevergabe.de published on 2026-11-19 (TED publication ID 806162-2026, internal reference ZV26-069). It shows buyer NRW.URBAN awarding Leiblein GmbH (Hardheim) the turnkey wastewater treatment plant for the second construction stage of the battery cell research production (Forschungsfertigung Batteriezelle) building in Münster for 2,963,226.94 EUR, on price alone (100%), with a contract conclusion date of 2026-11-17; the overview page of the NRW procurement platform shows the contract as already awarded.
Why the composition gap sets the sizing logic
The notice says plainly that the final constituents and loads of the process wastewater were not yet conclusively determined at tendering, which is why the design, the design assumptions, sampling, analysis, the operating-materials concept and the verification of performance had to be treated as particularly critical. Evaporators dislike such open ends: a feed whose solids, dissolved load or pH shifts shows up as fouling, foaming or corrosion. The flow pattern points the same way: with about 42 m³/d against a peak of about 5.2–5.3 m³/h, the buffer and the pre-treatment, not the evaporator, usually decide how steadily the plant runs.
Reading the notice quantities as a sizing reference
The values below describe that project, not your plant; the steps show how to use each of them.
| Parameter | Notice value | What it sets |
|---|---|---|
| Process wastewater, daily | about 42 m³/d | Daily volume |
| Process wastewater, peak | max. about 5.2–5.3 m³/h | Peak the buffer absorbs |
| Evaporator plant | about 40 m³/d | Evaporation capacity |
| Distillate | about 37.6 m³/d | Water leaving as distillate |
| Concentrate | about 2.4 m³/d | Residue for disposal |
| Pre-filtration | feed tank 12 m³; 2 × 9 m³ reactor tanks; belt filter 4 m² | Solids removal first |
| Feed and buffer tanks | 4 × 10 m³ (40 m³ in total) | Equalisation volume |
| Concentrate tank | 10 m³ | Storage before disposal |
| Solids load | about 1,500 kg/d; 10 containers of 1.5 t | Collection and removal |
- Check the evaporator against the daily volume. Feed rate = daily volume ÷ operating hours per day. The notice gives no operating hours, so its 40 m³/d cannot be turned into an hourly rate from the record alone; the operating regime has to come from the owner or the process package supplier.
- Check it again against the peak. Required buffer = (peak inflow − evaporator feed rate) × peak duration. The 40 m³ of double-wall PE feed and buffer tanks in the notice answer that equation in hardware.
- Split the feed into distillate and concentrate. Evaporated water = feed − concentrate. The notice figures add up: 37.6 m³/d of distillate plus 2.4 m³/d of concentrate equals the 40 m³/d stated for the evaporator plant (our arithmetic, not a figure given in the notice). The concentrate is what leaves the site for disposal or further dewatering.
- Take the solids out first. The notice places a feed tank, reactor tanks and a vacuum belt filter upstream of the evaporator and quotes a solids load of about 1,500 kg/d; solids reaching the evaporator settle or scale the heating surfaces.
- Leave the two daily figures as they are. The notice lists about 42 m³/d of process wastewater and an evaporator plant of about 40 m³/d without explaining how they relate; the reason for the gap is for the owner and the package supplier to confirm.
Choosing the evaporation route by operating condition
None of these routes is stated in the notice; the table compares them qualitatively, condition by condition.
| Operating condition | What it points to | What to watch |
|---|---|---|
| Composition not yet fixed | Staged design: sample, pilot or bypass test, then lock the values | Change after the order |
| Smaller, batch-wise flow, no steam on site | Vacuum evaporation | Electricity and cooling demand, cleaning between batches |
| Larger, steady flow, steam available | Multiple-effect evaporation | Steam supply, condenser load, more equipment |
| Steady continuous flow, energy cost dominant | Mechanical vapour recompression (MVR) | Compressor fouling, operation at low load |
| Sharp peaks relative to the daily volume | Larger buffer, smaller evaporator on longer hours | Peak duration |
| Concentrate to tanks; distillate reuse as rinse water | Storage and a disposal route; a quality specification | The notice states neither destination |
| Steam, power, cooling water and compressed air | Utilities and their cost decide the viable route | The notice gives none of these data |
Turnkey scope: what to pin down before the order
Within a new building that NRW.URBAN plans to build, complete with technical equipment, for the battery cell research production in Münster, the wastewater plant was let as one turnkey package: process design, supply, installation, electrical and control integration, instrumentation, control and automation, interface coordination, documentation, commissioning, trial operation, training, and support to acceptance and hand-over to the operator. When such a scope reaches an EPC contractor, we suggest five items are settled in writing:
- Scope and battery limits: which streams enter, where treated water and concentrate leave, which side provides each utility.
- Interfaces with the main process: wastewater generation points, the water-quality data each party supplies, the discharge destination.
- Sampling and analysis plan: who samples, where, how often and by which method, and how results feed the design.
- Design-assumption table and change mechanism: every load, concentration and operating hour assumed at order stage, and what happens when reality differs.
- Proof of performance: guaranteed feed rate, distillate and concentrate quantities and distillate quality, the acceptance test and its records.
The award was made on price alone; in our view the technical risk therefore sits in the specification and the assumption table, not in the evaluation.
Operating condition × equipment selection table
The HydropureWater catalogue on this site does not include the evaporator itself, so the rows cover upstream and ancillary equipment (pre-treatment polishing, chemical conditioning, solid-liquid separation and cake dewatering). They are references by operating condition, not equipment selected for the Münster project, in which HydropureWater has no part.
| Process step | Operating condition it serves | Equipment on this site (reference) |
|---|---|---|
| Polishing filtration | Fine particles and turbidity ahead of the evaporator | Multi-media filter |
| pH correction and chemical conditioning | Final pH control and dosing, as listed in the notice | Automatic chemical dosing system |
| Dewatering of pre-treatment solids | Solids captured upstream, ready for removal in containers | Plate and frame filter press |
For route-specific calculations, see our MVR evaporator capacity and sizing guide and the multiple effect evaporator design parameters guide; the process background is in our EV battery electrode slurry rinse wastewater treatment guide. See also our Germany country page.
RFQ checklist before you request a quote
- Daily volume, peak hourly flow and peak duration
- Water-quality data for each stream, with the sampling plan behind them
- Operating hours per day and per year, and planned downtime
- Concentrate disposal route and distillate destination, discharge or reuse
- Utilities on site: steam, electricity, cooling water and compressed air, with their cost
- Space, floor load and drain connections available for the plant
- The performance guarantee basis and the acceptance test method
Each item changes the capacity, the buffer or the route. With them in hand, use our request-a-quote page. This guide is our reading of a public award notice, not a tender document or bid advice; construction, commissioning and operation remain subject to the owner's later publications.
FAQ
Where does the Münster battery wastewater plant stand?
According to the award notice published on 2026-11-19, construction of the plant has been awarded to Leiblein GmbH by NRW.URBAN, with a contract conclusion date of 2026-11-17. The notice is an award record, not a completion report; the status of construction, commissioning and operation is to be taken from the owner's later public information.
Is the evaporator in the notice a vacuum evaporator?
The notice does not say. It lists an evaporator plant of about 40 m³/d and, separately, a vacuum belt filter in the pre-filtration stage. The type of evaporator is not stated, so it should not be assumed to be vacuum evaporation, multiple effect or MVR.
How is the evaporator sized when the wastewater composition is not fixed?
Set the capacity from the daily volume and the planned operating hours, set the buffer from the peak flow, and define the distillate and concentrate split as a guaranteed value that sampling and analysis will confirm. Keep a change mechanism in the contract for when the analysis differs from the assumption.