A public/private hybrid operating contract works best as a set of bounded, licensed roles, not a block of labor. The City of Ithaca's RFP for its Ithaca Area Wastewater Treatment Facility (IAWWTF) follows that logic: the City keeps recruiting its own staff, asks a contractor for a roster 7 days a week, 365 days a year including a licensed 4A operator, keeps the right to reduce or replace that staffing as hires arrive, and the Owner buys all supplies while the contractor provides maintenance labor. Owners should define duties role by role; bidders should price from the same role-level units, so the scope can shrink without reopening the price.
Source facts, briefly. The City's RFP document (Facility Overview) describes IAWWTF as a Type 4A, 13 MGD activated sludge plant averaging about 6 MGD, jointly owned by the City of Ithaca, the Town of Ithaca and the Town of Dryden. Designed for 17.5 FTE positions, it has significant staffing shortages, and the City has bought operating and compliance licensing services since 2023. The City's bid page lists the RFP, published 2026-11-23, as open, with electronic proposals due 2026-12-18 17:00; nothing has been selected or awarded.
HydropureWater is not a bidder, an operator or a consultant on this solicitation; what follows is our reading, not legal or bidding advice.
Why a staffing gap hits compliance and maintenance at once
Compliance rests on a ladder of qualifications; here the RFP requires a licensed 4A operator among the contractor's staff, qualified to submit the regulatory reports. When the roster is thin, the few licensed people are absorbed by shift coverage and the slow-burning tasks around their core duty slip first, such as operator training and report preparation. Maintenance degrades on the same schedule, because preventive work is the easiest task to defer on a short shift and deferral stays invisible until it becomes corrective work. Since the contractor must meet the effluent requirements of the existing SPDES permit using reasonable efforts at all times, the condition at handover is a commercial term, not a formality.
Tier the hybrid model by what each duty needs
The RFP does not state the number of posts, the shift pattern or the hours to be covered; those need confirming with the City. Our suggestion: tier the scope, because each tier drives cost and risk differently. For readers outside North America: 1 MGD = 3,785.41 m³/d, so 13 MGD ≈ 49,210 m³/d and 6 MGD ≈ 22,712 m³/d.
Tier by roster coverage and license level
Start with a duty matrix: for every shift, which tasks need the licensed 4A operator (regulatory reports, process-control decisions) and which can be carried by trainee operators, maintenance technicians, laboratory and administrative staff; the RFP asks for technical, laboratory, administrative and management qualifications. Then separate on-site presence from on-call coverage: the RFP requires staffing 7 days a week, 365 days a year and a round-the-clock emergency call service, but not whether nights and holidays are staffed on site, and that answer moves the lump sum most.
Tier by process area
| Process area | What it demands | What to confirm before pricing |
|---|---|---|
| Grit separation | Steady cleaning routines, debris handling | Duty of screens and grit units, odor control |
| Anaerobic digestion | Experienced operators, gas and confined-space safety | Digestion status, heating and mixing duties |
| Dewatering | Polymer dosing, solids handling, hauler interface | Who schedules hauling and disposal |
| Actiflo tertiary phosphorus removal | Close coagulant and polymer control | Who buys chemicals and microsand |
| Trucked-in waste receiving | Screening and load control at receipt | Receiving hours and acceptance rules |
Tier by contraction path
The City reserves the right to reduce or replace contracted staffing as additional City staff are hired, and will keep recruiting throughout the term. That is a pricing problem for the bidder unless the contract absorbs it. Our suggestions: give every position its own line, hours and rate; state which positions are severable; add a notice period for any reduction; add a knowledge-transfer item (standard operating procedures, OpWorks CMMS history, as-found asset condition) so a new City hire can take over a role without a gap; and name backups. We compare the underlying models in our article on wastewater plant O&M outsourcing models.
Tier by maintenance split
The RFP splits routine work cleanly: preventive maintenance follows the manufacturer's recommendations, the contractor supplies the labor, and the Owner purchases all supplies. Corrective maintenance is different: the contractor schedules and oversees it and provides pricing, but the Owner may use the contractor, other vendors or its own labor. Our suggestions: turn the manufacturer's recommendations into an asset-level schedule in OpWorks CMMS, each task marked as contractor labor plus Owner supply; define “supplies” explicitly (lubricants, spares, filter media, chemicals); and log deferred tasks with the Owner's acknowledgment.
How to read the 1-year and 5-year annual lump sums
The RFP asks for an annual lump sum for a 1-year term and for a 5-year term, broken down by names, titles, hourly rates and overhead factors and justified against personnel costs, overhead, how the overhead rate is derived, material and time. Our checklist:
- Build from named roles. The work plan must list each task's people and person-hours, with comparable projects and references; hours by rate by role should reconcile to the lump sum, with mobilization, training and handover costs visible rather than spread across the term.
- Fix the bases. State what the overhead factor applies to (labor only, or labor plus vehicles, instruments and training) and whether overtime, holiday cover, relief, standby and emergency call-outs are included or billed separately.
- State the escalation assumption. The posted RFP does not say how the annual figure may be adjusted across a 5-year term; bidders should declare it, owners should demand it.
- Read the commercial terms. City staff and joint-owner representatives shortlist applicants against a tabulation schedule in Appendix A; payment terms are negotiated after award, a non-appropriation clause applies, and an award does not itself execute a contract.
A wider discussion is in our 2026 buyer's guide to outsourced wastewater plant operation.
Process stage and equipment reference
Equipment makes and models at IAWWTF are not disclosed in the RFP; for plants with a similar process train, these products from this site are references by process stage only, not equipment used at this plant, and we do not provide plant operation services.
| Process stage | What the equipment covers | Product page on this site |
|---|---|---|
| Headworks, grit separation | Rotary screening that protects downstream equipment | Rotary Mechanical Bar Screen (GX Series) |
| Actiflo dosing | Coagulant and polymer preparation and dosing | Automatic Chemical Dosing System |
| Chemical phosphorus removal | High-rate solids separation after coagulation | High-Efficiency Sedimentation Tank |
| Dewatering | Batch dewatering of digested sludge | Plate and Frame Filter Press |
Background on the chemistry: our 2026 US utility guide to advanced phosphorus removal technologies.
Checklist before you draft the RFP or price a bid
For owners drafting a hybrid operating scope and contractors preparing a proposal, the items we would want confirmed in writing first:
- Flows, loading and scope: peak wet-weather flow, current loading, the units the contractor operates, and the rules for trucked-in waste receiving.
- Roster: number of posts, shifts and hours, on-site versus on-call coverage, relief and emergency call-outs.
- Compliance and laboratory: the current SPDES permit, the daily testing and periodic reports required; the RFP gives no limit values.
- Maintenance boundary: the definition of “supplies”, spare-parts stocking, access to OpWorks CMMS records, and how corrective work is authorized.
- Commercial and transition: the City's budget (not stated), payment terms, insurance and indemnity, evaluation weights, contract terms, handover protocol, training obligations and notice periods.
- Deadline: the RFP gives no time zone for 2026-12-18 17:00; submit early.
If the answers point to an equipment gap, at headworks, dosing, clarification or dewatering, gather peak flow, water quality, power supply, footprint and schedule and send them through our request-a-quote page. For regional context, see our United States wastewater treatment page.
FAQ
What stage is the Ithaca contract operations RFP at?
It is an open solicitation. The RFP was published on 2026-11-23 and proposals are due 2026-12-18 17:00. It lists selection on 2027-01-18 and a project kickoff meeting on 2027-01-22 as planned dates, and states that the contract award, if any, will be made by 2027-01-18. Nothing has been selected or awarded.
How does the hybrid model differ from full contract operation?
Hybrid: the City keeps employing and recruiting public staff, the contractor works alongside them within a City-set budget, and the City can cut contracted staffing as hires arrive. Full contract operation: the contractor runs the whole plant and fills every position.
What does the RFP not disclose?
The contract budget, the number of posts, shifts and hours, the City's current operating and compliance provider and its cost, equipment models, SPDES limit values and the evaluation weights. The tabulation schedule (Appendix A) and the contract terms (Appendix B) are not in the posted document; ask the City for both.