Start with the wastewater streams, not a treatment machine
Wastewater from a new SK On battery plant in Mexico should be managed through source segregation, mandatory characterization, treatment appropriate to each stream, controlled discharge or reuse, and documented monitoring. The Commission for Environmental Cooperation identifies spent-acid electrolyte and wastewater as key control areas for battery recycling and recommends pH adjustment followed by leachate testing of the resulting filter cake. It also identifies BOD, COD, TDS and TSS as relevant parameters. Mexico’s LGPGIR, NOM requirements and site-specific discharge or sewer permits must be confirmed with the competent authorities. The final treatment train cannot be selected without representative flow, pH, acidity, metals, FOG, COD, BOD, TSS and TDS data.
A new manufacturing battery plant should not begin equipment selection with a generic “battery wastewater” flow. The first engineering task is to map where water enters, what it contacts, how it is collected and where it can legally go. The project team should distinguish electrolyte-bearing drainage, process rinses, equipment cleaning, cooling-water blowdown, floor washings and sanitary wastewater. These streams may have different hazards, production schedules and regulatory routes.
Keep electrolyte-bearing and potentially hazardous streams as separate engineering cases. Sanitary flow or cooling-water blowdown must not be used to dilute influent results or obscure treatment demand. The CEC’s January 2016 technical guidelines, Environmentally Sound Management of Spent Lead-Acid Batteries in North America: Technical Guidelines, identify BOD, COD, TDS and TSS among parameters relevant to spent lead-acid battery management. Although the document addresses recycling rather than SK On manufacturing, its control logic remains applicable: characterize the wastewater, control acidity and solids, and prevent residues from becoming uncontrolled discharges.
| Design stream | Evidence required before equipment selection | Engineering decision |
|---|---|---|
| Electrolyte-bearing drainage | Representative flow, pH, acidity, COD, BOD, TSS, TDS, metals, oil and grease, and battery-specific constituents identified in the hazard review | Evaluate as a separate high-risk stream; do not dilute for characterization |
| Process rinses and equipment cleaning | Samples across normal production, startup, shutdown and cleaning cycles | Determine whether segregation, pH control, solids removal or a dedicated route is required |
| Cooling-water blowdown | Flow, chemistry, chemical additions and discharge restrictions | Assess reuse, segregation or discharge acceptance independently |
| Floor washings | Solids, metals, oil and grease, pH and wash chemistry | Define solids capture and wastewater treatment duties |
| Sanitary wastewater | Flow and applicable sewer or on-site treatment requirements | Keep separate from industrial compliance evidence unless the permit strategy expressly combines them |
The sampling campaign should represent normal production, startup, shutdown, cleaning and upset conditions. Use a written sampling plan with locations, durations, flow measurement and chain-of-custody procedures. Ask for laboratory results for flow, pH, acidity, COD, BOD, TSS, TDS, oil and grease, metals and any constituents identified by the process hazard review. A PLC-controlled chemical dosing system can later support controlled reagent addition, but its specification depends on the stream chemistry and the treatment objectives established by sampling.
Build a treatment train that follows the contamination
The treatment train should follow the contaminant pathway rather than apply every unit in a fixed sequence. Screening and equalization establish stable hydraulic conditions; pH neutralization addresses a confirmed acidity or alkalinity problem; solids, biological or polishing stages respond to measured duties; and final treatment follows the selected discharge or reuse route. The January 2016 CEC guidelines describe neutralizing wastewater through pH adjustment, but the reagent dose and process configuration must come from plant-specific characterization.
- Protect the headworks. Use durable mechanical screening to remove rags, plastics and fibrous debris before they reach pumps, clarifiers or membrane equipment. A rotary mechanical bar screen can be evaluated against the solids inventory and selected flow path, but screen aperture and capacity require project data.
- Equalize variable discharge. Provide equalization before pH adjustment or biological treatment so batch cleaning, rinsing and process discharges do not create short-duration loading peaks. Equalization volume must be derived from measured flow and operating sequences, not an assumed production multiplier.
- Adjust pH under control. Where sampling confirms acidic or alkaline wastewater, use controlled reagent dosing and verify the mixed-stream response. Calibrate pH instruments and define high- and low-dose alarms before contaminated flow enters the system.
- Remove solids deliberately. Route screenings, equalization sludge and chemical-treatment solids to sludge dewatering instead of allowing them to disrupt downstream treatment. A plate-and-frame filter press for wastewater sludge can be evaluated after the solids are characterized and the required filtrate and cake properties are defined.
- Apply flotation only where justified. Use dissolved-air flotation when testing confirms that suspended solids, oil and grease or colloidal material must be removed before biological treatment or polishing. The DAF system for battery-plant wastewater pretreatment should be selected against measured separation duties, not flow alone.
- Add advanced stages conditionally. Biological treatment, membranes, disinfection and reuse operations should enter the design only after influent characterization establishes organic load, solids level and the required effluent quality.
| Process stage | Required design evidence | Output to verify |
|---|---|---|
| Mechanical screening | Debris inventory, flow, screenability and maintenance access | Removal of rags, plastics and fibrous material |
| Equalization | Representative flow series and batch-discharge profile | Stable flow and load entering pH or biological treatment |
| pH neutralization | pH, acidity or alkalinity, chemical demand and mixing requirements | Controlled pH without destabilizing downstream treatment |
| DAF or equivalent solids removal | TSS, oil and grease, colloids and settleability | Reduction of specified suspended and floating contaminants |
| Biological, membrane or polishing stage | COD, BOD, TSS, TDS and final effluent objective | Compliance or reuse performance against the agreed route |
| Sludge dewatering | Solids generation rate, sludge chemistry and destination | Characterized filter cake and controlled filtrate return |
Filter cake and other sludge-bearing residues are not automatically suitable for disposal. The CEC’s January 2016 recommendation to perform leachate testing after pH adjustment provides the basis for a waste-characterization plan. The result must identify the authorized destination, handling requirements and acceptance criteria before the equipment supplier commits to a solids-handling arrangement.
Size equipment from peak flows and worst-case chemistry

Equipment sizing should use the plant’s verified hydraulic and chemical envelope, including simultaneous discharges and abnormal operating modes. Request average and peak hourly and daily flows, then identify which process areas can discharge at the same time. Include startup, shutdown, intensive cleaning and emergency or upset conditions. Hydraulic capacity alone does not establish treatment performance; the selected equipment must also meet the duty assigned to it.
The supplied DAF catalog covers 4–300 cubic meters per hour across 13 standard models. This is an available equipment envelope, not the required capacity for SK On. Match a model to the verified peak flow, anticipated wastewater characteristics, footprint, transfer constraints and redundancy requirements. For sludge dewatering, the supplied plate-and-frame range is 1–500 square meters of filtration area, with manual, hydraulic or fully automatic PLC-controlled operation. The selected area must follow from solids generation, dewatering performance, cycle time and filtrate return rather than the catalog maximum.
| Equipment | Supplied catalog envelope | Project-specific selection basis |
|---|---|---|
| DAF system | 4–300 cubic meters per hour; 13 standard models | Verified peak flow, TSS, oil and grease, colloidal behavior, treated-water objective and footprint |
| Plate-and-frame filter press | 1–500 square meters of filtration area; manual, hydraulic or fully automatic PLC control | Sludge quantity and chemistry, required cake condition, cycle time, filtrate destination and labor requirements |
| Automatic chemical dosing system | PLC-controlled injection; skid-mounted, pre-wired and factory-tested construction | Confirmed reagent demand, storage and transfer limits, mixing, controls, alarms and utilities |
A PLC-controlled chemical dosing system should be scoped for the confirmed coagulants, flocculants, pH adjusters or specialty chemicals, but the control system cannot substitute for an adequate chemical-demand calculation. Likewise, use the DAF capacity methodology for a Mexican industrial plant as a sizing workflow, not as evidence of SK On flow conditions.
Require each bidder to state the design basis, hydraulic loading, treated-water objective, utility demand, control philosophy, maintenance requirements and commissioning deliverables. Ask the filter press selection for battery manufacturing wastewater to identify its assumed sludge characteristics, acceptance tests and waste-handling interface. If those inputs are not stated, the offer is not comparable.
Confirm the Mexican compliance route before ordering equipment
The discharge route determines the treatment objective and therefore constrains equipment selection. Decide for each stream whether it will enter a municipal sewer, be treated on site, be delivered to a permitted hazardous-waste facility, be reused in the plant or follow another authorized route. Do not assume that a general environmental document establishes the SK On site’s discharge limits.
Confirm applicable NOM requirements, discharge authorization, hazardous-waste classification and sewer-acceptance conditions with the competent federal, state and municipal bodies. The CEC’s January 2016 technical guidelines identify LGPGIR—Mexico’s General Law for the Prevention and Management of Waste—and the federal environmental authorities PROFEPA and SEMARNAT. The same document lists NOM as the official Mexican standard framework. These references establish whom and what must be checked; they do not supply a project-specific permit condition.
The permit strategy should record each stream, its destination, governing authorization, acceptance criteria, monitoring points, flow measurement, alarm provisions and responsible operator. Sampling and recordkeeping provisions should continue through startup and routine operation. Where discharge to a sewer is contemplated, obtain the sewer authority’s acceptance criteria and confirm whether pretreatment is required; industrial pretreatment limits for battery and EV plants illustrates the type of external limit that must be verified rather than inferred.
Local infrastructure also requires confirmation. The ENR report, National Mexico Water Commission Embarks on $4.5-Billion Program, describes a broader Mexican wastewater-infrastructure deficit and major conveyance and treatment investments. It does not demonstrate that the receiving system for the SK On site has capacity or accepts the proposed discharge. The design team must therefore verify local conveyance, treatment capacity and any required pretreatment independently.
Do not order a final treatment train until the compliance route is documented, including handling of filter cake and other residues. A treatment line can be technically capable and still be noncompliant if the receiving sewer rejects the water, the waste lacks an authorized destination, or sampling and records do not satisfy the permit.
Commission with a sample-to-operation acceptance sequence

Commissioning should demonstrate that installed equipment meets the agreed treatment objective under representative operating conditions. The sequence begins with source characterization and mass-balance review, moves through factory and installation verification, and ends with a documented performance test using contaminated wastewater. Skipping the early steps leaves the acceptance test without a defensible reference condition.
- Close the design basis. Complete source characterization, mass balance, stream segregation and permit-route review before final process design and equipment purchase.
- Verify equipment before wastewater enters. Complete factory testing, installation checks, electrical and control inspection, instrument calibration and dry-run commissioning.
- Start each stage systematically. Introduce flow at controlled rates, establish operating stability and test each unit before relying on it for downstream protection.
- Run performance testing. Check pH, flow, TSS, COD, BOD, TDS and the applicable discharge parameters during startup, stabilization and representative operation.
- Prove residuals handling. Verify chemical dosing, sludge withdrawal, filter-cake handling, leachate characterization, sampling and chain-of-custody procedures.
- Retain the operating record. Record operating conditions, bypasses, alarms, maintenance actions and analytical results to demonstrate performance through routine operation.
The CEC’s January 2016 recommendation supports a waste-characterization plan for filter cake following pH adjustment. During commissioning, verify that the selected plate-and-frame filter press for wastewater sludge produces a residue consistent with the characterization plan and that filtrate is returned to the correct treatment stage.
Define acceptance tests before the test begins: sampling locations, flow conditions, analytical methods, parameter limits, number of samples, operating duration and response to alarms. A single satisfactory sample is not enough to establish sustained performance. Any bypass should be prohibited during the formal performance test unless the approved permit strategy expressly addresses it and the event is recorded and evaluated.
Use this framework to select treatment partners
Procure against a completed wastewater basis-of-design report, not an equipment name. Compare DAF, clarifier, integrated biological and other options only after assigning each proposed device a specific contaminant-removal duty. The bid package should attach flow data, characterization results, peak conditions, discharge criteria, residue destination and commissioning requirements.
A DAF system is appropriate when characterization establishes a duty to remove suspended solids, oil and grease or colloidal material and the verified flow is within the selected unit’s hydraulic envelope. The supplied DAF catalog covers 4–300 cubic meters per hour across 13 standard models; this range identifies available capacity, while the project data determine the model. An DAF system for battery-plant wastewater pretreatment should therefore be evaluated for contaminant-removal performance and integration with the rest of the train.
The supplied MBR catalog covers 10–2,000 cubic meters per day and describes integrated activated-sludge treatment with submerged PVDF membrane filtration. Consider an MBR where the design requires biological treatment with membrane separation and has a tighter or reuse-oriented effluent objective; do not use catalog capacity to infer SK On’s required flow.
| Selection condition | Relevant evaluation | Supplier evidence required |
|---|---|---|
| Measured solids, oil and grease or colloidal-removal duty | DAF separation performance and hydraulic fit | Design flow, loading basis, treated-water objective, utilities and control scope |
| Organic load plus tighter or reuse-oriented objective | Integrated biological treatment with membrane separation | Influent basis, permeate or final-water quality, membrane maintenance and operating strategy |
| Residual solids requiring dewatering | Plate-and-frame or another verified solids-removal method | Sludge basis, cycle time, cake condition, filtrate return and waste destination |
| Any award decision | Compliance risk and whole-life operating burden | Comparable references, performance data, commissioning support, chemical use, sludge handling, maintainability and clear O&M responsibilities |
Evaluate references with comparable wastewater characteristics rather than nominal throughput alone. Require treatment guarantees tied to defined influent and effluent conditions, utility consumption, sludge yield, control exclusions, commissioning tests, spare parts, operator training and O&M support. The award recommendation should state compliance risk, lifecycle operating costs, chemical use, sludge handling and maintainability separately. That keeps the decision auditable and prevents a generic equipment quotation from becoming the design.
Frequently Asked Questions
How much will wastewater treatment cost at the SK On battery plant in Mexico?
Treatment cost cannot be estimated responsibly until representative wastewater flows, chemistry and the selected discharge route are known. Request a supplier’s operating-cost basis, including chemical use, power, sludge handling, consumables, maintenance and analytical support. Do not accept a per-unit or annual price without the underlying flow, contaminant loading and waste-handling assumptions.
When should a DAF system be selected instead of an MBR?
Select DAF when testing establishes suspended solids, oil and grease or colloidal material as the immediate treatment duty and the selected unit covers the verified hydraulic peak. Consider MBR when the project requires integrated biological treatment with membrane separation and has a tighter or reuse-oriented effluent objective. These are process-duty decisions, not equipment-brand decisions.
What should be included in a wastewater treatment supplier’s technical proposal?
Require the design basis, treatment guarantees, utility consumption, sludge yield, control scope, commissioning tests, spare parts and O&M responsibilities. Also require the supplier to identify exclusions, assumptions, alarm handling, chemical-storage requirements and the performance data used to substantiate the guarantee.
Can SK On rely on general Mexican environmental guidance instead of project-specific permits?
No. The supplied research identifies LGPGIR, NOM, PROFEPA and SEMARNAT as relevant frameworks, but it does not provide SK On-specific discharge limits or waste classifications. The project must confirm the discharge authorization, sewer-acceptance conditions, hazardous-waste classification and authorized residue route with the competent authorities before finalizing the treatment concept.