Proposed sulfuric acid recovery for segregated chemical wastewater, with pretreatment, membrane testing and residual liquid sent to the existing plant.
Project Background
The client-supplied design basis is a segregated acid-bearing waste stream with a pH of 0.7, high conductivity and suspended solids, generated intermittently from chemical processing. The proposed scope covers collection, equalisation, oil and solids removal, membrane-based acid recovery, product validation and residual handling. No downstream wastewater treatment plant or water-reuse system is included.
Our Solution
The proposed system collects and equalises the segregated acid waste, then uses screening, dissolved air flotation and filtration to remove oil, suspended solids and membrane-fouling constituents. A membrane-based separation unit is proposed for sulfuric acid recovery, followed by laboratory and production compatibility testing before reuse. Concentrate or residual liquid is routed to the existing wastewater treatment plant, while oil-rich sludge is separated and dewatered for appropriate disposal. Final equipment sizing, recovery performance and product-acid quality will be established after representative testing confirms acid concentration, membrane compatibility, batch pattern and operating availability.
What We Asked First
Please confirm representative total and free sulfuric acid concentrations with analytical methods, batch volumes, discharge duration and frequency, available operating hours, new-acid concentration, and the production compatibility tests required for recovered acid.
Proposed Process Train
- 1Collect and equalise acid-bearing waste
- 2Screen and remove floating oil
- 3Coagulate and float suspended oil and solids
- 4Filter and condition the liquid
- 5Recover sulfuric acid by membrane separation
- 6Verify recovered acid for production reuse
- 7Transfer residual liquid to the existing wastewater treatment plant
- 8Segregate and dewater oil-rich sludge
For Similar Projects
Prepare representative wastewater samples, documented batch and operating data, acid analysis, production-acid specifications, existing plant interfaces, utility requirements, residual acceptance conditions and sludge disposal arrangements before final design.
Ref. A-031. Client identity is withheld under our client-confidentiality policy. Capacity is shown as a capacity class (design value rounded up to the next 5 at its second significant digit).