Sizing a 15 Ton per Day Solar Sludge Drying Facility: AKOSB, Turkey 2026

Sizing a 15 ton per day solar sludge drying facility means calculating the water it must evaporate, not the tonnage in its title. For the design-and-build tender issued for the Asım Kibar Organized Industrial Zone (AKOSB) in Turkey, bed area depends on four inputs: whether 15 ton/day is wet feed or dried product, the dry solids of the dewatered feed, the dry solids the outlet requires, and seasonal evaporation at the site. Our advice to bidders: confirm them in that order before pricing.

On 2026-11-23 the World Bank published notice OP00483146, an Invitation for Bids (reference GDOIZ-C1-WRK-034) to design and build a 15 ton/day solar sludge drying facility in the Asım Kibar Organized Industrial Zone (AKOSB), under the World Bank-financed Turkey Organized Industrial Zones Project (Project No. 171645; borrower: Ministry of Industry and Technology). The notice reads “Asm Kibar Organize Sanayi Bölgesi snrlar içerisinde 15 ton/gün kapasiteli Solar Çamur Kurutma yaplacaktr” (World Bank notice OP00483146, paragraph 2).

Step 1: confirm what the 15 ton/day figure measures

The notice gives only the capacity: no wet or dry basis, feed dry solids, target dry solids, bed area or location beyond the zone's name. These are to be confirmed in the tender document or with the purchaser, because each reading turns the capacity into a different evaporation load.

Written as a water balance, with dry solids conserved through the dryer, water to evaporate = feed mass × (1 − feed dry solids ÷ output dry solids). If 15 ton/day is the wet feed, that expression applies directly. If it is the dried product, the feed is 15 × output dry solids ÷ feed dry solids and the water to evaporate is 15 × (output dry solids ÷ feed dry solids − 1). Bed area follows that load. In kilograms, 15 ton/day = 15,000 kg/day.

Step 2: fix the inputs that drive drying bed area

Bed area then follows from five inputs:

InputEffect on sizeSource of the value
Basis of 15 ton/daySets the water to be evaporatedTender document, purchaser
Feed dry solids and rangeDrier feed, less water to evaporatePlant records, laboratory tests
Target dry solids and outletFixes the end point of dryingTender specification, receiving facility
Site climate by seasonSets water removed per unit area per dayLocal weather records
Available footprintCaps bed and storage areaZone layout plan

Effective bed area = water to be evaporated ÷ water removed per unit area per day, taken per season rather than as an annual average. The usual answer is a shoulder-season design plus a covered buffer where sludge fed in the cold, wet months waits for drier weather. Whether the buffer suffices or auxiliary heat is needed is the costliest decision in a design-and-build offer, and it also sizes turning, ventilation and corrosion protection.

Working conditions that decide the process route

  • Feed dewatering. Sludge fed straight from a thickener carries the most water and needs the largest bed area, which rarely fits inside an industrial zone; each step up in mechanical dewatering, preceded by polymer conditioning, removes part of the evaporation load.
  • Climate. A hot, dry summer lets the greenhouse outperform its design figure and shifts the risk to odour and overheating; a cold, wet winter collapses evaporation, so capacity must come from storage, auxiliary heat or both.
  • Footprint. Zone land is scarce; a constrained site pushes the design towards drier feed and more turning capacity.
  • Outlet for dried sludge. Co-incineration demands a drier, more consistent product than landfill, raising the target dry solids and the evaporation load.
  • Odour and leachate. An enclosed greenhouse needs forced ventilation with odour treatment and a drained floor returning liquid to the zone's treatment plant.

If the winter shortfall exceeds what a buffer can absorb, the choice is auxiliary heat inside the greenhouse or a thermal dryer instead; our comparison of sludge drying technologies and guide to sludge dryer advantages and disadvantages cover it. Because the bidder designs, the offer should fix the reference climate, the seasonal performance figures and their test conditions.

Working conditions × equipment selection

The products below are general equipment sold on this site as process references, not equipment selected for the AKOSB project.

Process stepCondition it addressesSite equipment (reference)
Mechanical dewateringWet feed, limited footprintPlate frame filter press
Polymer conditioningSludge that releases water poorlyAutomatic chemical dosing system
Drainage and leachate returnBed drainage, rainwater separationWater treatment parts, valves and media

How the tender is run

The notice fixes these terms; anything else is governed by the tender document.

ItemAs stated in the notice
MethodNational competitive bidding by Request for Bids under the World Bank's November 2020 IPF procurement regulations
Procurement groupWorks
EligibilityOpen to all eligible bidders as defined in those regulations
Contracting partyAsım Kibar Organized Industrial Zone
Tender documentDigital copy, fee 1,000 TL
SubmissionSealed envelope by 2026-12-15 10:30; no electronic bids; late bids not evaluated
OpeningPublic, 2026-12-15 10:45
Bid securityAt least 3,500,000.00 TL
National lawNot subject to Law No. 4734 or Law No. 4735

Evaluation and qualification criteria are, per the notice, on the ministry's OIZ tender announcements page. Because bids are sealed envelopes delivered to a stated address, overseas equipment or process suppliers usually contribute through a domestic bidder as joint venture partner or subcontractor; that is our suggestion, not a purchaser requirement or legal advice. For a comparable package, our report on wastewater reuse and sludge drying in Balıkesir covers another zone and another contract under the same World Bank project; see also our Turkey page.

RFQ checklist before asking for a quote

A supplier can only price measured inputs. Send these with the inquiry:

  • Sludge origin and the dewatering equipment already installed
  • Feed dry solids as a typical value and a range
  • Power supply, footprint and height limits at the site
  • Odour and leachate requirements, operating days and staffing

With the five inputs above, request a quote; the proposed bed area can then be checked against the water balance.

FAQ

What stage has the AKOSB solar sludge drying facility reached?

As of the invitation for bids published on 2026-11-23, the project is at the open tender stage: bids are due by 2026-12-15 10:30 and open in public the same day at 10:45. Award, contract signature and start of construction depend on the purchaser's subsequent notices.

Does “15 ton/day” mean wet sludge or dried sludge?

The notice does not say. It gives a capacity of 15 ton/day without calling it feed or product, so the basis must be confirmed in the tender document or with the purchaser before any bed area is calculated; a dried-product basis implies more water to evaporate than a wet-feed basis.

How can an overseas supplier take part in this tender?

Through the national competitive bidding described above: a sealed envelope due by 2026-12-15 10:30 with a bid security of at least 3,500,000.00 TL; electronic bids are not accepted. Overseas suppliers usually join a domestic bidder, our suggestion to verify in the tender document.

References

  1. World Bank procurement notice OP00483146 - Invitation for Bids GDOIZ-C1-WRK-034: Design and Construction of the Solar Sludge Drying Facility for the Asim Kibar Organized Industrial Zone (AKOSB)

Related Articles

Nov 27, 2026

Industrial Zone Wastewater Reuse & Sludge Drying: Balıkesir, Turkey 2026

A World Bank contract award notice published on 2026/11/09 records an 18-month works contract for t…