Peel Region says odours from the G.E. Booth Water Resource Recovery Facility in Mississauga are expected to fall by more than 90 per cent once modernization work is completed, according to a report published November 12, 2026. The project is on track for completion in 2027.insauga.com
Key takeaways
- Approximately half of the odour-mitigation program is scheduled for completion by the end of 2026, with most of the work planned for 2027.insauga.com
- Peel Region expects odours to drop by more than 90 per cent after the upgrades are finished.insauga.com
- The G.E. Booth facility has a capacity of 518 million litres per day and serves municipal wastewater from residential, commercial and industrial customers.insauga.com
- The province provided $35 million in August 2024 to support system extensions and new features, including an aeration tank and filtering systems.insauga.com
Odour-control upgrades move ahead
Residents in southeast Mississauga have reported intermittent foul odours near the G.E. Booth facility for decades, with some describing the smell as frequent and overpowering during hot or humid weather, while others said it is occasional or rarely noticeable.insauga.com
Peel Region said the 71-year-old plant is being upgraded to reduce odours and modernize the facility.insauga.com
“G.E. Booth is being upgraded to reduce odours and modernize the facility. The local community can expect odours to drop by more than 90 per cent once this work is done,” Peel Region said in its online description of the odour-removal efforts.insauga.com
Approximately half of the odour-mitigation program is scheduled to be completed by the end of 2026, while the bulk of the work is planned for 2027.insauga.com
Expansion supports continued growth
Built in 1955, G.E. Booth is the largest wastewater treatment plant in Peel and treats municipal wastewater from residential, commercial and industrial customers.insauga.com
The facility serves east Mississauga, east Brampton and part of York Region, and its current capacity is 518 million litres per day.insauga.com
Peel Region said the upgrades are intended to address continued population growth, including the Lakeview Village development in Mississauga’s southeast corner, which is bringing approximately 16,000 new homes to the area.insauga.com
In August 2024, the provincial government provided $35 million for the expansion effort, supporting extensions to water systems and new features such as an aeration tank and filtering systems.insauga.com
Specification read
The reported plant capacity is 518 million litres per day, equivalent to 518,000 m³/day; the source does not provide enough information to calculate a population equivalent because the applicable per-capita factor or design population is not reported.insauga.com
At this scale, a municipal treatment train ordinarily comprises screening, primary clarification, biological treatment, and tertiary treatment or disinfection, with solids-handling and odour-control systems integrated around the process. The G.E. Booth project bears directly on biological-treatment aeration and filtration because the reported upgrades include an aeration tank and filtering systems, while the odour-mitigation work addresses containment and treatment-related emissions.insauga.com
If your plant has flow around 518,000 m³/day and you are reviewing an odour-control, aeration or filtration upgrade, this is what it means for you: the project demonstrates that odour mitigation can be integrated with capacity and process modernization rather than treated as an isolated environmental issue. The reported aeration-tank and filtering-system additions are relevant reference points for municipal wastewater planning, while air and dust treatment should be assessed against the site-specific odour sources and capture system rather than selected from headline capacity alone.
Procurement teams should distinguish the reported 518,000 m³/day installed scale from the programme’s odour-control objective: more than 90 per cent is the expected reduction in community odour after completion, not a reported treatment-flow increase.insauga.com
FAQ
How much of the odour upgrade is scheduled to be complete by the end of 2026?
Approximately half of the odour-mitigation program is scheduled for completion by the end of 2026, with the bulk of the work planned for 2027. The odour-removal program is therefore still in progress, and the more-than-90-per-cent reduction refers to the expected result once the work is done.insauga.com
What is the project cost?
The supplied report identifies $35 million received from the provincial government in August 2024, but it does not provide a total project cost or a breakdown for the odour-mitigation program.insauga.com A procurement estimate should therefore be developed from the required scope, site constraints and performance criteria rather than treating the reported funding as the full project price.
When should odour-control equipment suppliers be selected?
The source does not report procurement dates, tender schedules or equipment lead times. It states that approximately half of the programme is due by the end of 2026 and most work is planned for 2027, so suppliers need the detailed work packages and commissioning sequence before selecting delivery periods.insauga.com
What operating data should a buyer request when selecting an odour-control supplier?
The report does not provide flow variability, odour-concentration measurements, compound profiles or capture-system airflow data. Those inputs are missing from the supplied information, so a supplier should be asked to demonstrate performance against site-specific odour conditions and the plant’s stated objective of a more-than-90-per-cent reduction after completion.insauga.com