On a small sequencing batch reactor (SBR) package plant, the choices that decide whether a bid is workable are made before bid opening: which SBR equipment the design is built around, which UV disinfection unit fits the room, which controls platform the whole plant speaks, and how long-lead equipment is sequenced against a Vermont winter. Our read of the Town of Waitsfield's Addendum No. 1 is that this bid favors contractors who arrive with named chemical feed, UV, sludge aeration, controls and SCADA suppliers already priced, and who have carried the winter shutdown and the equipment deposit in their schedule and cash flow.
The first-hand source is Addendum No. 1, dated November 24, 2026, issued by DuBois & King, Inc. to prospective bidders for the Town of Waitsfield Wastewater Treatment Facility – Contract 1 (engineer's project no. 227947). It forms part of the contract documents and modifies the bidding documents dated November 10, 2026 (PDF p. 1). Bids are due December 28, 2026 at 11:00 a.m. local time, electronic bids are accepted, and the pre-bid meeting took place on November 19, 2026 (p. 1).
The scope, per Attachment 3, is a new 0.1 MGD SBR treatment facility with a new building, leachfields, and associated pumps, valves and piping (p. 28). Bids have not been opened and no award has been made. HydropureWater is not a bidder, supplier or adviser on this project; what follows is our procurement guidance, not bidding or legal advice.
Suppliers have to be named before the job is won
The addendum rewrites Article 11.02: the apparent successful bidder, and any other bidder so requested, must give the owner a list of the proposed subcontractors or suppliers for the following portions of the work within five days after bid opening: controls, site work, concrete, chemical feed, UV treatment, sludge aeration and SCADA (p. 2). The pre-bid notes add that horizontal directional drilling was dropped from that list and the sludge equipment, concrete, UV, chemical feed and SCADA vendors were added (p. 10). Five days is too short to obtain quotes, so, in our view, every supplier a bidder intends to name should be lined up before December 28, 2026.
Our advice is to ask each supplier for a bid-stage quotation that can be accepted inside that window without re-pricing. It should state:
- Scope of supply and battery limits: what the supplier delivers, and what the contractor installs, connects or builds around it.
- The design basis being priced, and the influent and effluent parameters the contractor has to warrant.
- Lead time counted from a defined trigger (approved submittal, deposit received, release to fabrication), not from the order date.
- Commercial terms: deposit amount and due date, price validity, warranty start, spare parts and start-up support.
- Compliance documents, including the origin statements needed for Build America, Buy America.
Three clauses move cost onto the contractor early. If Aqua Aerobic Systems, Inc. requires a deposit before shipping the SBR equipment, that deposit is not eligible for reimbursement and will not be compensated separately from the measurement and payment terms (Question 9, p. 5). Retainage is 5% (p. 11). The Aqua-Aerobic bid item will be adjusted by the ENR index at contract signing (p. 11). In practice: finance the deposit inside the price of the related bid item, avoid double-counting escalation on the item that is already indexed, and use the question deadline of December 11, 2026 to ask for the deposit amount and schedule, which the addendum says will be addressed in Addendum 2.
UV disinfection: alternates now go through the submittal process
Specification 46 6616 keeps the basis of design: a non-contact UV disinfection system, model C1t.06022, manufactured and supplied by Enaqua, “or approved equal”. The earlier text required alternate manufacturers to be pre-qualified at least 30 days before the bid. The addendum deletes that route: Enaqua is not a pre-qualified vendor for this project, alternate systems are a proposed substitution for review in the submittal process, and the physical constraints of the available space for a substitute UV system would need to be evaluated during submittal review (p. 3). Question 10 adds that the UV vendor has not been preselected (p. 5).
Read together, these lines keep the basis-of-design name as the anchor while approving no alternate in advance. Submittal review normally happens after contract award, so the contractor carries the risk of a late rejection. We suggest pricing both paths, the basis-of-design unit and the alternate, with the difference and the review risk visible. Before quoting an alternate UV system, our checklist is:
- Envelope and weight against the room and the installation route. A bidder asked whether the unit can be carried down the stairs to its basement location or whether the elevated slab must wait for it; the owner left sequencing, means and methods to the contractor and said an equipment cut sheet can be provided in Addendum 2 (Question 27, p. 7).
- Hydraulic fit: connection size, head loss at peak flow, and the upstream quality that sets UV transmittance.
- Electrical and controls fit with the plant's Allen-Bradley platform, including who programs the integration.
- Maintenance clearance around lamps and quartz sleeves, and validation documents showing dose at the design flow.
The addendum does not publish UV dose, lamp count, lamp power or unit dimensions; treat them as unconfirmed until Addendum 2. The variables that drive UV sizing are covered in our UV disinfection system design parameters guide.
One controls platform from the SBR panel to SCADA
Two specification edits tighten the controls package: section 26 0917 (programmable controllers) adds “Allen-Bradley” before “Substitutions”, and section 26 9002 replaces “EOS Research” with “Allen-Bradley or approved equal” (p. 3). The edits answer a bidder who asked whether an Allen-Bradley PLC supplied inside the SBR manufacturer's system could serve plant-wide SCADA communication (Question 35, p. 8). The owner also confirmed there is no pre-qualified controls integrator (Question 13, p. 5).
For suppliers this is an interface question more than a brand question. The SBR manufacturer, the UV supplier, the chemical feed supplier and the SCADA integrator each deliver controllers, and the bid only holds together if panels, I/O and programming responsibility fit without gaps or overlaps. Which panels are shown on the drawings, who builds them, and the I/O list for SCADA vendors are deferred to Addendum 2 (Questions 11, 12 and 14, p. 5). Until then, a controls quotation should include:
- A panel-by-panel schedule: tag, location, supplier, and the instruments wired into each panel.
- The network and protocol each device will use to reach the plant SCADA, and who supplies the switches and cabling.
- Who writes the integration programming, who witnesses loop checks, and which start-up reports and training the contractor must hand over.
- A price split between hardware, programming and commissioning, so scope moved to or from the SBR package can be valued quickly.
Long-lead equipment against the winter shutdown
The schedule question came from a bidder, who asked whether a winter shutdown is expected and stated that the SBR system has up to a 40 week lead time (Question 22, p. 7). The owner's answer covered only the shutdown: a winter shutdown is expected, see Attachment 1. No lead time was confirmed. On time, the addendum says the construction schedule is the contractor's responsibility, that shutdown days will not count against the contract days, and that the planned shutdowns in Attachment 1 increase the contract time by the length of the shutdown (Question 21, p. 7). Attachment 1 records 365 days for substantial completion and 455 days for final completion, liquidated damages of $2,000 per day following preliminary substantial completion and $1,500 per day following final completion, and shutdown change orders planned at contract signing and after preliminary substantial completion if the plant must wait for Contract 2 to supply wastewater for start-up (p. 10). Tree cutting is limited by time of year (p. 11).
With time counted in contract days and a shutdown excluded, the critical chain is submittals, approval, fabrication, delivery, setting equipment in place, tank testing and start-up. The equipment that gates the structure matters most; the basement UV unit is the example already raised in this bid. We suggest building the schedule around three arrival cases rather than one promised date.
| Equipment arrival | Effect on site | Our suggested preparation |
|---|---|---|
| Before the shutdown | Structure can close over the unit | Confirm access route and setting plan; do not hold the slab open |
| During the shutdown | Site closed; unit needs storage | Agree storage and warranty terms with the supplier before shipping |
| After the shutdown | Setting date becomes the first activity | Keep independent piping and electrical work ahead of it |
Two more exposures belong in the price. The contractor remains responsible for the project for up to 365 days after preliminary substantial completion at no additional cost (Questions 2 and 18, pp. 4 and 6). The SBR manufacturer's performance guarantee applies only after successful start-up (Question 20, p. 6), and the duration of biological start-up is deferred to Addendum 2 (Question 3, p. 4). Ask the SBR supplier for a lead time split into submittal, fabrication and shipping phases, each with its own trigger, and for the start-up support included in the price.
The revised bid schedule: planned dates
The addendum revised the bidding schedule to allow more time (Question 15, p. 6). These are the planned dates in that table; the 2027 entries have not yet occurred.
| Milestone | Planned date | What to have ready |
|---|---|---|
| Advertise project | November 10, 2026 | Original bidding documents |
| Pre-bid meeting | November 19, 2026 | Meeting notes (Attachment 1) |
| Addendum 1 | November 24, 2026 | Acknowledge it in the bid form |
| Questions due | December 11, 2026 | Written questions on deposits, panels, UV cut sheet |
| Addendum 2 | December 17, 2026 | Check the issuing office website |
| Bid opening | December 28, 2026, 11:00 a.m. | Named suppliers with priced quotes; list due within five days after bid opening |
| Bid analysis | January 7, 2027 | Supplier quotes still valid |
| Selectboard review | January 11, 2027 | Supplier quotes still valid |
| Notice of award | January 18, 2027 | Supplier list already submitted |
| Contract signing authorized | February 8, 2027 | Deposits and submittals ready to release |
Federal funding clauses: check the supply chain, not the headline
The owner confirmed that the project holds no Build America, Buy America (BABA) waivers for any equipment (Question 34, p. 8), and the bid form asks bidders to certify familiarity with BABAA and AIS requirements (p. 24). We do not offer a legal reading of either clause. The procurement point is that every equipment package now needs a traceable origin record: where the steel was melted and formed, where the manufacturing steps happened, and which components would not qualify. Ask each supplier for a written statement per item before naming them, and price a domestic-content alternative separately if a package cannot be documented.
Wages work the same way. Davis-Bacon wage rates will be re-checked before the final addendum and updated there if they have changed, and certified payrolls are required with pay applications (p. 11). For items that are mostly labor, such as the UV installation item, price the work at the wage determination in force and confirm whether supplier field service technicians working on site fall under it.
Sizing logic for a 0.1 MGD SBR package and the bid form
Attachment 3 describes an SBR treatment facility with a capacity of 0.1 million gallons per day (p. 28), or 0.1 MGD. Converted, as our calculation rather than the owner's: 0.1 MGD × 3,785.41 = 378.5 m³/d, an average-day figure. This addendum publishes no influent characteristics or effluent limits, so the relationships below are what to put to the SBR supplier, not numbers to fill in:
- Volume exchanged per cycle = daily flow ÷ cycles per day; basin volume = exchanged volume + sludge retained between cycles + freeboard.
- Peak flow and peak organic load, not the average day, set the decanter, blower and aeration sizing.
- With a single basin, inflow arriving during settle and decant must be equalized or held; a second basin changes the cycle logic and the footprint.
The owner confirmed that tank and pump-station dimensions may vary from the plans as long as the required volume, critical elevations, concrete requirements, access and cover over the tanks are achieved (Question 6, p. 4). That makes the supplier's volume basis more important than the drawn dimensions. The bid form in Attachment 2 separates equipment from installation, so quotations should be mapped to the right line before pricing (pp. 17–18).
For scale, the owner's estimated opinion of probable construction cost for Contract 1 is in the range of $4.8 million to $5.9 million (Question 8, p. 5). That is an opinion of probable cost, not a bid ceiling, and the addendum does not publish a breakdown of that estimate by bid item, so we would use it only as a sanity check on the total bid, not to back-calculate equipment budgets.
| Bid item | Stage | To collect from the supplier |
|---|---|---|
| Item 17: SBR system equipment, lump sum | Biological treatment | Design basis, deposit, lead time by phase |
| Item 18: SBR tanks and foundations | Civil works | Required volume and critical elevations |
| Item 20: chemical feed systems | Chemicals | Chemical type and dose, to be confirmed |
| Item 22: 9,000 gallon precast sludge tank with diffuser piping, 4 each | Sludge storage and aeration | Tank schedule and diffuser layout |
| Item 24: UV treatment installation, labor and overhead | Disinfection installation | Labor at the applicable wage rates |
| Item 25: sludge blowers, 3 each | Sludge aeration | Blower model and power, to be confirmed |
Operating conditions and equipment selection by process stage
HydropureWater's catalog does not include SBR process equipment, and its UV sterilizers are conventional units rather than the non-contact type named in this specification. For the auxiliary stages of a small plant, the table lists our current products by process stage. These are products presented on this website for reference only: none of them is selected equipment for the Waitsfield project, and nothing here is a claim that an item would be accepted as an “approved equal” to the project's basis of design.
| Process stage | Role in a small package plant | HydropureWater reference |
|---|---|---|
| Headworks screening | Removes rags and debris before pumps and basins | Rotary Mechanical Bar Screen (GX Series) |
| Chemical feed | Skid-mounted dosing for coagulation, pH control or emergency dosing | Automatic Chemical Dosing System |
| Disinfection | Conventional UV sterilizer, not the non-contact type in this specification | UV Sterilizer for Water Treatment |
| Compact biological treatment | Underground integrated plant for small communities; a package alternative, not SBR equipment | Underground Package Sewage Treatment Plant (WSZ Series) |
These are the stages where a supplier can quote from a clear parameter sheet rather than a full process design, which is why the checklist below matters. For the treatment cycle itself, see our guide on how an SBR works; for the wider market, see our page on wastewater treatment in the United States.
RFQ checklist before you ask for a quote
Whether you are a general contractor collecting bid-stage quotes or an owner's representative comparing package plants, the same information decides whether quotations are comparable. Our checklist of what to send:
- Flows: average day, peak hour and peak day, plus any allowance for infiltration.
- Water quality: influent characteristics, effluent limits, and the sampling basis for the performance guarantee.
- Site: footprint, room dimensions and access routes, groundwater and frost conditions, and the seasons when work is allowed.
- Power and controls: supply characteristics, backup power, and the PLC and SCADA platform the equipment must join.
- Schedule: bid date, award date, delivery window, shutdown periods and the start-up sequence.
- Commercial terms: deposits, price validity, warranty and performance guarantee start, spare parts and training.
- Compliance: domestic-content documentation and wage requirements that apply on site.
Send these parameters with your inquiry through our request-a-quote page and ask for the quotation to be broken down by bid item, so it can be dropped straight into the bid form.
FAQ
Where does the Waitsfield SBR project stand now?
Addendum No. 1 was issued on November 24, 2026. Bids are due December 28, 2026 at 11:00 a.m. local time, and Addendum 2 is planned for December 17, 2026. The 2027 dates in the schedule, from bid analysis to authorization of contract signing, are planned dates. No contract has been awarded.
Why do bidders have to name suppliers within five days after bid opening?
The revised Article 11.02 requires the apparent successful bidder, and any other bidder the owner requests, to list the proposed controls, site work, concrete, chemical feed, UV treatment, sludge aeration and SCADA suppliers within five days after bid opening. Because that window is too short to obtain fresh quotes, suppliers should be selected and priced before the bid is submitted.
How will an alternate UV system be reviewed after this addendum?
Enaqua's C1t.06022 remains the basis of design “or approved equal”, but Enaqua is not a pre-qualified vendor and no UV vendor has been preselected. Alternate systems are handled as proposed substitutions in the submittal process, where the space available for the substitute unit and other considerations would need to be evaluated. The 30-day pre-qualification route for alternates has been deleted.
Is the 40 week lead time for the SBR equipment confirmed?
No. The 40 week figure appears in a bidder's question. The owner's answer stated only that a winter shutdown is expected and referred to Attachment 1. The addendum confirms no SBR equipment lead time, so ask the supplier for a lead time split into submittal, fabrication and shipping before relying on any figure.
Can the contractor recover the SBR equipment deposit?
No. If Aqua Aerobic Systems, Inc. requires a deposit before shipping, the deposit is not eligible for reimbursement; paying it is the contractor's responsibility and it will not be compensated separately from the measurement and payment terms. The addendum says more on deposit requirements will come in Addendum 2.