In a wastewater treatment plant upgrade tender, the base bid is the scope every bidder must price in full, while bid alternates are separately priced options that the owner may add or deduct when the contract is awarded. If the boundary is vague, bids cannot be compared like for like. A current example is item 20 of the Sioux City, Iowa, City Council agenda of November 23, 2026: a resolution to award the base construction contract for Phase 1 of the City's wastewater treatment plant improvements to PKG Contracting, Inc. for $292,376,900 and to reject all bid alternates, as City staff recommend in the meeting packet. Whether the Council passed it, and under what resolution number, is confirmed only by the adopted resolution and the meeting minutes.
What the Sioux City council documents say
Item 20 on page 4 of the City Council agenda of November 23, 2026 (PDF) names the resolution: a contract with PKG Contracting, Inc., of Fargo, North Dakota, for $292,376,900 for the Wastewater Treatment Plant Facility Plan Phase 1 Improvements Project.
The Council meeting packet of November 23, 2026 (PDF), pages 247–250, holds the Request for City Council Action from the Public Works Director and the draft resolution: staff asks the Council to award the base contract at $292,376,900 and reject all bid alternates. The draft leaves the resolution number blank, so these documents record a proposed award, not the Council's decision.
The packet reports that the project was bid on October 29, 2026 and that three bids were received. The base bids were $292,376,900 from PKG Contracting, Inc., $308,649,600 from Rice Lake Construction Group and $322,722,493 from Hawkins Construction Company, against an Engineer's Estimate of $325,000,000. According to the packet, the PKG base bid is $32,623,100, or about 10.04%, below that estimate.
Hazen and Sawyer, P.C., of Minneapolis, Minnesota, which prepared the plans and specifications, reviewed the bid packages and PKG's qualifications and likewise recommended awarding the base bid contract to PKG and rejecting all bid alternates.
The packet also notes an irregularity in PKG's Alternate Bid Item No. 1, which was unclear as to whether the amount was additive or deductive; Hazen and Sawyer determined that rejecting all bid alternates negates this irregularity, and no other discrepancies or irregularities were identified in PKG's bid package. The packet recommends rejecting all bid alternates but does not state its reason.
The packet describes Phase 1 as improvements to the plant's headworks, primary clarifiers, primary sludge pumping, intermediate lift station, aeration basins, blowers, final clarifiers, return activated sludge pumping, cake storage, odor control, standby generators, electrical systems and plant controls, plus associated demolition and supporting infrastructure. The project must be completed by December 31, 2031 and is funded with State Revolving Funds (SRF) under CIP 539-006. These pages list process areas, not equipment models or equipment vendors.
The packet also lists the Council's alternatives: it may choose not to award the contract, and the bids may be evaluated further or the project documents revised and reissued for bid. An item on the agenda is therefore not the same as an award.
Sioux City decision points and what to check
The right-hand column is our suggestion, not a City requirement.
| Decision point | Fact in the council documents | What to check |
|---|---|---|
| Bid structure | Three bids; lowest base bid $292,376,900 | Are base bid and alternates listed separately? |
| Budget check | Engineer's Estimate $325,000,000; low bid $32,623,100 lower | Does the base bid leave room for other project costs? |
| Other bidders | Rice Lake Construction Group $308,649,600; Hawkins Construction Company $322,722,493 | Are all bids priced on the same base scope? |
| Procurement path | CMAR from April 2026; GMP not accepted July 2026; bids received October 29, 2026 | Which route sets your quoting timing and risk? |
| Alternates | Award base bid, reject all recommended; direction of Alternate No. 1 unclear; no reason given | Is each alternate marked as add or deduct and priced on its own? |
| Award status | Item 20 on the agenda of November 23, 2026; outcome not in the packet | Check the adopted resolution and minutes before treating the award as final |
Base bid, alternates and the CMAR switch
The points below are general procurement guidance from this site, not Sioux City rules and not bidding or legal advice; the bid documents of each project govern.
Base bid and bid alternates
- Base bid: the complete scope in the bid documents without any alternates. It must stand on its own, because the owner may award it alone.
- Add alternate: optional scope, priced separately, that the owner may accept to increase the contract amount.
- Deduct alternate: scope the owner may remove, with its price subtracted from the base bid.
Mark each alternate as an addition or a deduction
The Sioux City packet records an irregularity in Alternate Bid Item No. 1 over whether its amount was additive or deductive. In our view, a supplier should label every alternate as an addition or a deduction, with its amount, unit and quantity, and name the base-bid items it changes.
CMAR guaranteed maximum price and competitive bidding
Under the Construction Manager at Risk (CMAR) route, the owner engages a construction manager early, and the manager later offers a guaranteed maximum price (GMP) for the defined scope. In traditional competitive bidding, contractors price the completed bid documents and submit competitive bids, which are opened publicly. The packet records that Sioux City first advertised the project in April 2026 under CMAR, did not accept the GMP submitted in July 2026, advertised it for conventional bidding on September 15, 2026 and received bids on October 29, 2026; it gives neither the GMP amount nor the reasons. For suppliers, the route decides who asks for a quote and when: usually the construction manager under CMAR, the bidding contractors before the bid opening under traditional bidding.
Supplier quote checklist for base bid and alternates
This is our suggested preparation checklist for suppliers, not a list of the City's requirements.
- Define the base bid boundary. State what is included (equipment, auxiliaries, instrumentation and controls, freight, unloading, installation or supervision, commissioning) and what is excluded.
- Price every alternate separately and mark its direction. State whether it adds to or is deducted from the base bid, give its amount with unit and quantity and its effect on schedule and interfaces (foundations, power, piping, controls), and state any dependency on another alternate.
- Write substitutions properly. For an approved equal, describe exactly what differs in capacity, materials, controls, footprint or lead time and attach the supporting documents; do not hide the change in the base bid.
- State validity and escalation. Give the validity period and say how changes in material prices, freight or exchange rates are handled.
- Check the bid form before submission. Make sure each amount sits on the right line, the base bid stands alone and the totals add up.
- Handle clarifications in writing. After the bid opening, answer requests for clarification in writing and keep the record, because clarifications can affect the award.
Related reading on this site
Equipment pages on this site are general references published by HydropureWater, not equipment selected for the Sioux City project; HydropureWater claims no role in that project.
FAQ
What is the difference between a base bid and bid alternates?
The base bid is the full scope every bidder must price, complete on its own. Bid alternates are separately priced additions or deductions that the owner may accept or reject when the contract is awarded.
Why would an owner reject all bid alternates?
The Sioux City meeting packet does not state a reason. In general, the owner weighs alternates against the project budget and its priorities; here the reason can only be confirmed from the City's own documents.
How is a CMAR guaranteed maximum price different from a competitive low bid?
A guaranteed maximum price comes from a construction manager engaged early; a competitive low bid is the lowest bid submitted by competing contractors and opened publicly. Sioux City did not accept the GMP submitted in July 2026 and received competitive bids on October 29, 2026.
Is the $292,376,900 an equipment budget?
No. It is the lowest construction base bid for Phase 1, submitted by PKG Contracting, Inc. and listed in the council packet. The packet names the process areas to be improved but no equipment vendors, and it does not break the amount down by equipment.
Has Sioux City awarded the contract?
Item 20 of the City Council agenda of November 23, 2026 is a resolution to award the base contract to PKG Contracting, Inc. for $292,376,900 and reject all bid alternates, as the Public Works Director recommends in the meeting packet. The agenda and the packet do not record the outcome; whether it passed, and the resolution number, rest on the adopted resolution and the meeting minutes.