Reliance Industries Limited awarded VA Tech Wabag Limited an EPC contract worth over ₹1,000 crore for desalination and remineralisation facilities in Jamnagar, Gujarat, according to a report published on 15 November 2026. megaproject.com
Key takeaways
- The EPC contract is worth over ₹1,000 crore and covers design, engineering, equipment supply, installation, commissioning and performance testing. megaproject.com
- The desalination plant will initially process 8,400 cubic metres per hour and is expandable to 12,600 cubic metres per hour. megaproject.com
- A separate remineralisation facility will have a capacity of 3,000 cubic metres per hour. megaproject.com
- Execution is scheduled in phases over 25 months. megaproject.com
Contract covers full plant delivery
Reliance Industries Limited awarded the EPC contract to VA Tech Wabag Limited for facilities in Jamnagar, Gujarat, according to the report published on 15 November 2026. megaproject.com
The scope includes design, engineering, equipment supply, installation, commissioning and performance testing for both the desalination and remineralisation facilities. megaproject.com
The desalination plant is designed for an initial throughput of 8,400 cubic metres per hour, with expansion to 12,600 cubic metres per hour. megaproject.com
Technology scope and delivery schedule
The project will use seawater reverse osmosis, ultrafiltration and advanced clarification systems, alongside limestone filters, chemical dosing, water storage and pumping infrastructure. megaproject.com
Execution is scheduled in phases over 25 months, making the award a full-delivery project rather than a single-equipment purchase. megaproject.com
Specification read
The reported 8,400 cubic metres per hour initial desalination rate equals 201,600 cubic metres per day, or 201.6 MLD, while the 12,600 cubic metres per hour expansion rate equals 302,400 cubic metres per day, or 302.4 MLD. The source describes the latter capacity as approximately 302 million litres daily, and the separate 3,000 cubic metres per hour remineralisation facility equals 72,000 cubic metres per day. megaproject.com
No population-equivalent figure was reported, so a population served cannot be calculated from the available information. The reported treatment train is seawater reverse osmosis supported by ultrafiltration and advanced clarification, with limestone filtration, chemical dosing, storage and pumping; this is a seawater-treatment and water-recovery scope rather than a conventional municipal biological wastewater process. megaproject.com
If your plant enquiry resembles a seawater reverse-osmosis project with a flow of 201.6 cubic metres per day, expansion to 302.4 cubic metres per day, remineralisation at 72,000 cubic metres per day and phased delivery, the significance is a plant-scope signal: the award bundles process design, balance-of-plant equipment, commissioning and performance testing under one EPC contract. megaproject.com
For related process-selection context, compare MBR vs Conventional Activated Sludge for Mining Wastewater 2026 with DAF vs. Clarifier for Chemical Wastewater in Eustis (2026), or review our Water Purification and Industries We Serve pages for adjacent treatment applications.
FAQ
What is the reported value of the Jamnagar desalination and remineralisation EPC contract?
The contract awarded to VA Tech Wabag Limited is worth over ₹1,000 crore. Its scope covers design, engineering, equipment supply, installation, commissioning and performance testing for the desalination and remineralisation facilities in Jamnagar, Gujarat. megaproject.com
What capacity will the desalination plant have?
The plant will initially process 8,400 cubic metres per hour, equivalent to 201.6 cubic metres per day on an hourly-rate basis, and can expand to 12,600 cubic metres per hour, equivalent to 302.4 cubic metres per day. The source reports the expanded rate as approximately 302 million litres daily. megaproject.com
How long will the project take?
Execution is scheduled in phases over 25 months. The report does not provide a commissioning date for individual phases or additional procurement milestones, so buyers assessing lead time would need those details confirmed during tendering or supplier discussions. megaproject.com
What treatment processes are included?
The specified scope includes seawater reverse osmosis, ultrafiltration, advanced clarification systems, limestone filters, chemical dosing, water storage and pumping infrastructure. A separate remineralisation facility will have a capacity of 3,000 cubic metres per hour. megaproject.com