Set the Gabon Design Basis Before Sizing
Size a containerized sewage treatment plant for Gabon by establishing the served population or metered process-water flow, average and peak sewage demand, influent load, required effluent quality, and available footprint. Calculate average flow first, apply a declared peak method for hydraulics, size biological capacity on organic load, and then use V = Q × HRT to check tank volume. Finally, verify that the required capacity fits the selected modules and that each module can reach the site. No Gabon-specific flow allowance or discharge criterion was supplied, so those project inputs and the applicable approval route must be confirmed before purchase.
Start with a one-page design-basis sheet, not a tank catalogue entry. Record the design year, served population or metered process-water flow, average daily sewage flow, highest-day sewage flow, peak-flow method, influent BOD5, COD and TSS, required effluent quality, receiving-water discharge route, footprint, soil conditions, power availability, backup-power arrangements and remote-control requirements. Use metered data when available; otherwise document the survey or neighbouring-town basis used to develop the project assumptions.
The containerized sewage treatment plant sizing method should be treated as a method, not as a source of Gabon-specific allowances. The available information does not establish a Gabon-specific per-capita allowance, receiving-water rule or approving authority. Request those items from the owner, operator and relevant local authority, and retain the documents used in the final design basis.
Calculate Average and Peak Demand
Keep the time basis attached to every flow figure, as a highest-day estimate is not an average-day flow. Under GB 50014-2021 §4.1.14, the sewage allowance is 90% of the selected water-use allowance, and the output category and time basis follow the input. For a population-based calculation, document the selected water-use allowance, apply the 90% conversion, retain the daily time basis and then calculate:
- Average daily flow: Qavg = served population × selected average sewage allowance.
- Highest-day flow: Qhighest-day = served population × selected highest-day sewage allowance.
- Peak hydraulic flow: Qpeak = Qavg × declared dry-weather peak factor, using a project-approved method.
The supplied residential water-use table in GB 50013-2018 spans 50–320 L per person per day across zones and city-size bands. Do not treat that range as a universal Gabon rate. Select the appropriate row, document why it represents the site, and keep residential and combined domestic allowances separate. If the project is an industrial estate, food plant, hospital or other non-residential development, use the meter or process brief as the flow driver and use population only as a cross-check.
The containerized sewage treatment plant sizing method should make the time conversion visible. This prevents a highest-day allowance from being multiplied incorrectly by an average-day peak factor and gives the reviewer a traceable calculation rather than an unexplained flow number.
Match the Process Route to the Wastewater

Choose the process route based on the wastewater duty rather than the tank label. Biological capacity should be based on average flow, organic load and solids retention time, while channels, pumps and pipes should be checked against peak flow. The supplied process guidance gives anaerobic residence time of 1–2 h, anoxic residence time of 2–10 h and solids retention time of 10–22 days where simultaneous nitrogen and phosphorus removal is the objective.
For a high-organic industrial stream, treat the organic load as a separate sizing case and settle the pretreatment requirement before selecting biological capacity. The integrated A/O sewage treatment package may suit a route requiring separate biological zones, while an integrated MBR wastewater treatment system requires a clear effluent specification and membrane-performance basis. Neither route should be selected before the project’s influent and discharge requirements are documented.
Use the following worksheet to compare the discharge route or influent problem with the process decision and the data needed to settle it.
| Discharge route or influent problem | Governing rule or process option | What data settles it |
|---|---|---|
| Domestic wastewater with a conventional biological treatment objective | Evaluate an A/O route using average flow, organic load and solids retention time. | Influent BOD5, COD and TSS; average and peak flow; required effluent quality; receiving point. |
| Required effluent quality calls for membrane separation | Evaluate an integrated MBR route and its membrane, solids handling and performance requirements. | Effluent targets, membrane design basis, pretreatment needs, operating and maintenance inputs. |
| High-organic industrial discharge | Make pretreatment a separate case and size the biological stage from the organic load. | Process-water meter records, wastewater analysis, batch or production schedule and pretreatment test data. |
| Uncertain or phased treatment requirement | Allow for treatment stages that can be added in sequence rather than forcing one package to meet every future objective. | Project phasing, available footprint, interim discharge route and confirmed approval requirements. |
The Cotorro case in the ASCE database illustrates why route selection should follow the required outcome: it separated preliminary and primary treatment with disinfection, secondary biological treatment and tertiary nutrient removal into three phases. Its reported final characteristics—BOD 18 mg/L, TSS 13 mg/L, total phosphorus 4 mg/L and total nitrogen 22 mg/L—belong to that case and are not Gabon discharge limits.
Calculate Tank Volume and Module Capacity
Calculate each tank’s hydraulic volume from:
V = Q × HRT
where V is tank volume, Q is the flow assigned to that tank and HRT is hydraulic residence time. Convert Q and HRT to matching units before multiplying, and state whether the check uses average flow, peak flow or another documented duty. Apply the same discipline to organic loading: calculate the load from flow and influent concentration, then compare it with the selected process’s stated loading rate and solids retention time.
The supplied containerized-unit range is 0.5–10 m³/h, or 12–240 m³/day, depending on capacity. Compare the calculated requirement against that range rather than assuming one unit is sufficient. If it is not, calculate the required module count and assess whether parallel modules improve redundancy and peak-flow handling; otherwise, ask the supplier to propose a larger process package.
Check the assembled dimensions against the delivery route. The supplied assemblies range from about 3 × 1.5 × 2 m to 16 × 3 × 3.5 m depending on capacity, and the largest assemblies cannot travel in a standard dry container because width and height control the route. Treat these figures as loading guidance, not as approval for a Gabon port, road or installation method.
Ask the supplier to state the shipping configuration—dry container, open-top or flat-rack container, or break-bulk cargo—and to confirm lifting points, road and port constraints, site access and installation method. A containerized UF water treatment system is not a substitute sizing basis for sewage; use it only where the specified treatment train and project duty genuinely require that equipment.
Verify the RFQ and Pre-Signature Scope

Accept a quotation only when the supplier’s sizing document and commercial scope state the same design basis. Require average flow, peak flow, organic load, process route, hydraulic residence time, solids retention time, unit count, dimensions and performance assumptions to appear together. Any omitted value is an unresolved design assumption and should be returned for completion before price acceptance.
Ask the supplier for the actual project inputs: flow records, water-meter data, wastewater analysis, receiving point, required effluent quality and available footprint. Do not allow a quotation to hide generic assumptions behind “typical domestic sewage.”
Use this RFQ acceptance table to identify inclusions, exclusions and red flags before signing.
| Quote line item | Technical scope to specify | Red flags to check before signing |
|---|---|---|
| Process capacity and performance | State average flow, peak flow, organic load, process route, HRT, SRT, unit count, influent basis and process guarantees linked to stated effluent conditions. | Flow or loading omitted; “typical sewage” substituted for analysis; guarantee not linked to defined influent and effluent conditions. |
| Treatment train | Specify screening, solids removal, biological treatment, clarification, disinfection, sludge handling, controls and required ancillaries. | Sludge handling, disinfection or controls excluded while the performance guarantee assumes their presence. |
| Delivery and installation | Identify container configuration, dimensions, weight, lifting points, road or port route, site access, offloading, installation and commissioning responsibilities. | Delivery stops at port or gate; no lifting points, offloading method or installation boundary; local access not checked. |
| Commissioning, training and warranty | Define testing, acceptance testing, operator training, documentation, operating support, warranty exclusions and spare parts. | Commissioning or training omitted; acceptance criteria absent; warranty excludes the duty conditions on which the quotation is based. |
The packaged sewage treatment plant option comparison can help organise alternatives, but the quotation must still identify which party supplies each boundary item. Require the final sizing sheet, general arrangement, process schematic, equipment schedule, performance basis and delivery plan to be attachment references to the purchase order.
Further Reading
Frequently Asked Questions
What technical information is needed before accepting a containerized sewage treatment plant price?
Before accepting the price, require the supplier to state average and peak flow, organic load, process route, HRT, SRT, unit count, dimensions, influent and effluent assumptions, treatment scope, delivery configuration and commissioning responsibility in one document. If the site flow, analysis or receiving point is unknown, request the owner’s flow records, wastewater analysis and discharge requirements rather than accepting an unpriced generic assumption.
How should process performance be guaranteed for a Gabon project?
Require the guarantee to state the design average flow, peak flow, influent BOD5, COD and TSS, required effluent quality and operating conditions. Also require the supplier to define how performance will be tested and who resolves failure. Do not transfer figures from another country’s case into the guarantee; the Cotorro results are a project example, not a Gabon limit.
What delivery information should be confirmed before placing the order?
Require the quotation and shipping plan to identify the container configuration, assembled dimensions, weight, lifting points, road or port route, site access, offloading method, installation boundary and commissioning responsibility. For a road or port shipment in Gabon, ask for local logistics confirmation; the published assembly dimensions alone do not establish that a shipment is transportable or installable.
Which compliance documents must the buyer request?
Request the identified receiving point, required effluent quality, applicable discharge route, and written confirmation from the relevant local authority of the approval and inspection pathway. The available information does not establish a Gabon-specific receiving-water rule or approving authority, so the project cannot be treated as compliant merely because the quoted package meets a generic performance claim.