Establish the Eritrea Project Design Basis
Size a containerized sewage treatment plant in Eritrea from the required service population or measured flow, applicable per-capita sewage allowance, peak-flow method and organic load—not from the container size. GB 50014-2021 §4.1.14 converts a water-use allowance into a sewage allowance at 90%. A cited example uses 120 L per person per day of residential water use, giving 108 L per person per day of sewage. No cited source establishes an Eritrea-specific allowance, permit limit or tariff, so confirm those inputs locally before quotation.
Begin with the current and forecast served population, development schedule, seasonal occupancy and any temporary-use pattern. Record whether flow comes from metered data or a per-capita allowance, and identify who will confirm population, water use, network-flow and growth assumptions. For residential developments, the packaged sewage treatment options for a residential development illustrate why the source and time basis must remain visible in the sizing sheet.
Keep three duties separate: average hydraulic flow, peak hydraulic flow, and average organic and solids load. Require each quotation to state whether its capacity is nominal, average, highest-day or peak. Do not let a container catalogue dimension become the plant size. The MBBR versus MBR container sizing worksheet provides a useful comparison framework, but its assumptions must be replaced with project-specific Eritrean inputs.
Define the terms used in the worksheet: peak wastewater flow is the maximum flow condition used for hydraulic checking; organic load is the mass rate of biodegradable pollutants used to size biological treatment; and a peak factor converts a reference flow to the applicable peak condition. State the time basis of each value.
Calculate Flow and Load Before Choosing a Container
Carry the population, allowance and time basis through the calculation before selecting equipment. GB 50014-2021 §4.1.14 uses a sewage allowance equal to 90% of the water-use allowance. In the cited worked example, 120 L per person per day is converted to 108 L per person per day of residential sewage. A served population of 10,000 people then gives about 1,080 m³ per day on a highest-day basis—not an average daily flow. These figures demonstrate the method; they are not Eritrea design inputs.
- Calculate design flow from the selected population and documented sewage allowance, or use measured flow for non-residential developments.
- Convert the flow to the required time basis before applying a peak method.
- Size biological stages using average flow, organic load, solids retention time and required process conditions.
- Apply the applicable peak-flow method for hydraulic equipment and pipes.
- Check volume against the required hydraulic residence time using V = Q × HRT, with units consistent.
For peak calculation, GB 50014-2021 Table 4.1.15 lists Kz values of 2.7 at 5 L/s, 2.4 at 15 L/s, 1.9 at 100 L/s and 1.5 at 1,000 L/s and above. Confirm the applicable table category and whether the project flow is combined domestic sewage before using it.
Obtain laboratory and operating data for BOD5, COD, suspended solids, fats, metals, pH and temperature. A high-strength stream may require upstream equalization, oil and grease removal or pH adjustment rather than simply a larger biological container; use the high-COD pretreatment specification as a scope-development reference.
| Discharge route or influent problem | Governing rule or process option | What data settles it |
|---|---|---|
| Residential or mixed domestic development | Use population and a documented sewage allowance, retaining the highest-day or average time basis through the calculation. | Current and forecast population, local water-use evidence, development schedule and network-flow records |
| Hotel, camp, industrial estate or other non-residential use | Use measured flow or the process brief as the primary basis; use population only as a cross-check. | Water-meter record, occupancy pattern, process discharge and seasonal variation |
| Variable or high-strength wastewater | Check equalization and conditioning before sizing the biological stage. | Hourly flow series, BOD5, COD, suspended solids, fats, metals, pH and temperature |
| Discharge to sewer or receiving environment | Confirm the receiving route and applicable local consent; do not transfer a catalog effluent value into a permit requirement. | Discharge point, authority correspondence, reuse conditions and any written consent |
Select MBBR or MBR Against Site Conditions

Choose the process route from the locked influent and effluent basis, not from container count or nominal capacity. MBBR sewage treatment and MBR wastewater treatment both use biological treatment, but MBR adds membrane separation. The decision must consider load variability, effluent target, footprint, operator capability, maintenance access, redundancy and lifecycle cost.
Use MBBR when the project can meet the biological design load with adequate retention time and the required effluent quality does not depend on membrane separation. Use MBR when the confirmed effluent target and site constraints justify membrane solids separation and the operator can control flux, cleaning and replacement. The hollow-fiber ultrafiltration membranes used in many MBR units have a nominal pore size on the order of 0.04 microns, which supports suspended-solids retention, but nominal pore size alone does not demonstrate pathogen removal or permit compliance.
Require MBR evidence covering sustainable flux under the specified influent, membrane-integrity testing where pathogen removal is required, cleaning intervals and membrane life under stated operating conditions. For higher-strength streams, assess equalization, oil and grease removal or pH adjustment before biological treatment. The integrated MBR membrane bioreactor and modular MBR membrane modules are equipment references; their catalogue capacity does not establish the Eritrean project size.
Check Shipping, Site Utilities and Residuals
Confirm freight feasibility after calculating the required treatment capacity. The sizing basis indicates that capacity determines the number of units, while each unit’s dimensions determine whether it ships as a dry container, open-top or flat-rack container, or break-bulk cargo. Obtain the current port, road, lifting and electrical requirements from the relevant project and logistics parties; the cited research does not establish Eritrea-specific freight limits.
Give the bidder a verified site pack containing pad dimensions, drainage and lifting access, power quality, backup-power arrangement, chemical-storage needs, safe chemical-delivery route, and maintenance clearances around and above the equipment. A factory-tested wastewater treatment system may reduce site work, but it still requires compatible utilities and service access.
Define the liquid and residuals boundary. Equalization, disinfection, sludge storage and dewatering may sit outside the container. Sludge handling remains a separate design item; specify whether removal, transport and disposal are included. A plate-and-frame filter press may be proposed for dewatering, but its suitability depends on the sludge characteristics. Likewise, a rotary mechanical bar screen addresses a defined pretreatment duty and should not be included merely as a generic accessory.
Turn the Design Basis into a Quotable Scope

Require every bidder to submit the same sizing basis and technical boundary. Ask for design and peak flow, daily load basis, process train, container count and dimensions, connected utilities, confirmed effluent target, test method and exclusions. Require performance claims to name the influent and testing conditions; a statement that output is “well below” a threshold is not useful without its test basis.
Compare total installed and lifecycle cost rather than equipment price alone. The comparison must cover treated capacity, pretreatment, civil works, connections, redundancy, energy, chemicals, commissioning and maintenance. Also make shipment, factory testing, wastewater plant commissioning, training, spare parts, local service support, warranty and site acceptance testing contractual acceptance criteria.
| Quote line item | Technical scope to specify | Red flags to check before signing |
|---|---|---|
| Design capacity and process | Population or measured flow, sewage allowance, time basis, peak method, organic-load basis, process train and container arrangement. | Only one nominal capacity; peak flow omitted; container dimensions used as the sizing basis |
| Effluent performance | Permit or reuse target, sampling point, analytical methods, influent conditions and applicable performance standard. | Catalog values presented as guaranteed project performance without test conditions |
| Site and utilities | Pad, drainage, power, backup power, chemicals, connections, lifting, access and local installation work. | Connected utilities or civil works omitted without a stated exclusion or allowance |
| Residuals and pretreatment | Scope for screening, equalization, disinfection, sludge storage, dewatering, removal and disposal. | Assumes the container handles every stream or that sludge disappears into the liquid train |
| Delivery and acceptance | Shipment mode, factory test, commissioning protocol, training, spares, warranty, service support and acceptance samples. | “Factory tested” or “ready to operate” stated without procedures or acceptance criteria |
Frequently Asked Questions
Why do population, flow and organic load all need to be known before selecting a container?
Population and a documented sewage allowance establish a preliminary flow basis; measured flow is preferable where population is not the driver. Peak flow determines hydraulic adequacy, while organic load determines biological capacity. A container selected from any one figure alone may pass the wrong duty. Require the bidder to reconcile all three and identify which conditions govern.
What should be included in the installed price, and what should be listed as exclusions?
Require the price to state whether it includes delivery, lifting, placement, foundations, connections, power, commissioning, training, spares and initial chemicals. Require civil works, external tanks, pretreatment, disinfection, sludge removal, disposal and long-term service to appear either in the price or in a priced exclusion list. No defensible price can be requested until the design flow, load, site utilities and scope boundary are defined.
What evidence should a supplier provide for delivery, commissioning and site acceptance?
Ask for the proposed shipping configuration, factory-test scope, site commissioning procedure, training plan, warranty terms and local spares and service arrangements. Performance acceptance should identify the influent basis, sampling point, analytical methods and pass/fail criteria. This converts generic delivery claims into auditable contract conditions.
How should a buyer qualify a supplier when Eritrean permit and site conditions remain unconfirmed?
Check whether the supplier can document performance for the specified influent, explain its design calculations, state sustainable operating conditions and support the plant after delivery. Request confirmation from the relevant Eritrean project and logistics parties for discharge consent, utility requirements, road access and lifting constraints. Until those confirmations are obtained, catalog claims cannot replace project-specific compliance or delivery risk review.