Elected officials said on 16 November 2026 that the international plant treating Tijuana sewage lacks millions in funding needed to complete its expansion in Mexico, with the project’s full secondary-treatment stage still short of secured money. The Coronado News
Funding gap widens as expansion advances
The South Bay International Wastewater Treatment Plant currently treats up to 35 million gallons per day, while the expansion is designed to raise capacity to 50 million gallons per day. The Coronado News reported that the first major construction contract for the expansion was awarded in September 2026, with construction beginning soon afterward. The Coronado News
Design for the 50 million-gallon-per-day expansion was reported complete on 13 November, while the full design and approval process had been slated for October 2026. The Coronado News The United States and Mexico signed a memorandum of understanding in July 2025 that identified December 2027 as the project deadline. The Coronado News
| Project item | Reported figure or status |
|---|---|
| Current treatment capacity | Up to 35 million gallons per day |
| Expanded capacity | 50 million gallons per day |
| Funding secured to rehabilitate and expand the plant | $650 million |
| Expected additional cost for full secondary treatment | About $270 million more |
| Revised contract for primary-treatment expansion | $552 million |
Every figure in the table was reported by The Coronado News.
The International Boundary and Wastewater Commission awarded PCL Construction a revised $552 million contract on 13 October for expansion of the plant’s primary-treatment facilities, with substantial completion scheduled for 2031. The Coronado News That contract does not include expansion of the secondary-treatment facilities, which IBWC spokesman Frank Fisher said would require additional funding. The Coronado News
Secondary treatment remains unsecured
Ryan Williams, SANDAG’s manager of government affairs, said the work needed to bring the plant to 50 million gallons per day of secondary treatment was expected to cost about $270 million more, and that this funding had not been secured. The Coronado News The secondary-treatment expansion was targeted for 2030, according to what IBWC told the San Diego Water Board earlier in the year. The Coronado News
IBWC had not indicated when it anticipated funding for secondary treatment or what effect the gap could have on the project timeline. The Coronado News San Diego Water Board Executive Officer David Gibson said on 10 November that IBWC was reporting a $275 million shortfall against the projected full-design construction cost for the secondary-treatment system. The Coronado News
“The board’s expectation is that the plant will be expanded by 2030 and at full secondary for …whatever they ultimately design,” Gibson said. The Coronado News The shortfall therefore directly affects the stated delivery objective for the biological treatment stage, although the source did not report whether an adjusted completion date has been adopted. The Coronado News
Specification Read
The reported expansion scale is 50 million gallons per day, equivalent to approximately 189,300 cubic metres per day, based on the source’s stated capacity. The Coronado News The source did not report a population-equivalent figure, influent flow, BOD, COD or other design-basis values, so a population-equivalent comparison cannot be made from the supplied information. The Coronado News
This project bears directly on the secondary, or biological, treatment stage. A treatment train of screening, primary treatment, biological treatment and tertiary or disinfection treatment would place the funded primary works upstream of the unfunded secondary works; the source does not specify whether the final configuration will use A2O, MBR, MBBR, SBR, UASB or another biological process. The Coronado News
If your plant looks like a cross-border municipal wastewater plant with roughly 189,300 m³/day of expanded capacity, biological treatment needed for U.S. standards, and secondary-stage funding still open, this means that procurement schedules and technical specifications must separate primary-facility delivery from the still-unfunded biological package. The Coronado News Buyers evaluating equipment for a project of this type can review our municipal wastewater equipment and integrated sewage treatment resources for initial scoping, while industries we serve provides further plant-type context. Wastewater handling at a Mexico assembly plant offers a related Mexico-focused reference for industrial planning. The Coronado News
FAQ
How much funding is still needed for secondary treatment at the Tijuana plant?
SANDAG estimated about $270 million more was needed to bring the plant to 50 million gallons per day of secondary treatment, while the San Diego Water Board reported a $275 million shortfall against the projected full-design construction cost. The Coronado News The source did not reconcile the two figures, so buyers should not treat them as interchangeable.
What delivery dates apply to the different parts of the expansion?
The United States–Mexico memorandum of understanding identifies December 2027 as the overall project deadline, and the secondary-treatment expansion was targeted for 2030. The Coronado News The $552 million primary-facilities contract has substantial completion scheduled for 2031. The Coronado News The source reported that IBWC had not said how the funding shortfall would affect the schedule.
What is already funded and contracted?
The plant expansion has $650 million in secured funding for rehabilitation and expansion, and IBWC awarded PCL Construction a revised $552 million contract for primary-treatment facilities. The Coronado News The source did not provide a supplier-selection package for secondary treatment, including its process configuration or procurement schedule.
Which treatment stage carries the greatest funding risk?
The secondary-treatment expansion to 50 million gallons per day lacks secured funding, while the revised contract covers primary-treatment facilities. The Coronado News The source did not report the selected biological process, so process-specific lead times and supplier lead times cannot be established from the supplied information.