Confirm the monitoring obligation before choosing equipment
Utilities required to monitor PFAS in wastewater should first confirm the governing jurisdiction, permit, order or written program rather than assume that drinking-water standards also govern wastewater discharges. Monitoring should cover the analytes, matrices and sampling points needed to answer the compliance or risk question, including source-control decisions where industrial users may contribute PFAS. San Francisco’s 2025 program illustrates a broader approach: the SFPUC began regular testing for 40 PFAS compounds using EPA Method 1633 at influent, effluent and biosolids. The sampling plan should also specify laboratory quality controls, data validation, exceedance response, reporting, and the treatment or pretreatment action triggered by each result.
Begin with the document that creates the requirement. Obtain the applicable permit, consent decree, agency order or written monitoring agreement from the utility compliance staff, and record the jurisdiction, receiving authority, identifier, reporting dates, renewal provisions and named responsible office. A requirement should be classified before it drives procurement:
| Discharge route or influent problem | Governing rule or process option | What data settles it |
|---|---|---|
| Effluent discharge | Verified permit, order or agency monitoring condition | Permit identifier, outfall, parameter list, monitoring frequency, reporting limit, action level and responsible authority |
| Industrial-user discharge | Industrial pretreatment permit or verified agency source-attribution request | Industrial-user inventory, screening results, applicable pretreatment limits, sampling authority and pass-through provisions |
| Drinking-water system | Separate drinking-water monitoring requirement | Written confirmation from the authority that the drinking-water scope is separate from the wastewater program |
| Utility-wide risk assessment | Proposed voluntary risk-control program | Board policy, risk rationale, budget authorization, decision objectives and intended follow-up actions |
| Biosolids or PFAS-bearing solids | Site-specific disposal, reuse or land-application requirements | State and local biosolids rules, disposal contract, application records and receiving authority confirmation |
Do not use the EPA drinking-water maximum contaminant levels described in the cited source as wastewater limits. The quoted scope is national drinking-water standards: in April 2024, EPA set 4 parts per trillion individually for PFOA and PFOS and 10 parts per trillion for PFNA, PFHxS and HFPO-DA. Those values do not, by themselves, establish a wastewater discharge limit. Ask the permit authority directly whether monitoring must cover drinking water, wastewater, industrial-user discharges or more than one route.
Choose the matrices and sampling points that answer the risk question
Select matrices and locations by the decision they must support, not by convenience. The SFPUC tests wastewater influent, effluent and biosolids at the Southeast and Oceanside Treatment Plants. That broader design is relevant because PFAS can partition, transform and recirculate across solids, liquids, foam, aerosols and off-gas. An outlet sample may establish an effluent condition without explaining where the PFAS entered the system or where it went.
| Discharge route or influent problem | Governing rule or process option | What data settles it |
|---|---|---|
| Treatment performance | Paired influent and effluent sampling | Representative samples from documented locations, collection times, flow data and treatment-unit operating conditions |
| Effluent compliance | Permit-specific outfall monitoring | Outfall designation, permit condition, sampling method and representative discharge data |
| Biosolids management | Biosolids sampling linked to the disposal route | Dewatering or storage location, sampling procedure, destination and applicable acceptance criteria |
| Industrial-user source attribution | Representative industrial-user sampling and pretreatment review | PFAS source inventory, industrial-user screening data, candidate facilities, sampling authority and applicable industrial pretreatment limits and source control considerations |
For source attribution, obtain the industrial-user inventory and screening results from the pretreatment team before selecting candidates. A sampling plan should explain how representative industrial-user samples will be compared with plant influent, which facilities are excluded and why, and how upstream control responsibility will be assigned. A broader utility-wide program may still be necessary, but it should not be treated as proof that a particular industrial user is the source.
Define the analytical package and laboratory acceptance criteria

Make laboratory quotations comparable by requiring the complete analyte list and matrix-specific analytical conditions. The SFPUC states that in 2025 it began regular wastewater testing for 40 PFAS compounds using EPA Method 1633. That example demonstrates the value of naming the method and analyte count, but it does not establish a mandatory wastewater program elsewhere.
Require each laboratory to quote:
- The analyte list, method and intended use for each matrix.
- Sample containers, preservation instructions, holding time and shipment requirements.
- Reporting limits, method-specific qualifiers and the usable concentration basis.
- Blank requirements, matrix-specific quality controls, acceptance criteria and corrective actions.
- Chain-of-custody requirements and the treatment of rejected or qualified data.
- Complete electronic data deliverables, including case narratives and quality-control results.
- Whether the quotation covers influent, effluent, biosolids, industrial-user samples or a combined program.
Require the laboratory to state where a result is reported on a usable concentration basis, how qualifiers are assigned and how data that fail validation are handled. A single reporting limit across liquid and solids matrices is not a sufficient comparison basis. The RFQ should also require laboratory staff to explain any matrix-specific deviations and to deliver the underlying quality-control information needed for utility review.
Turn monitoring data into an operational response
Define the response path before samples are collected. The monitoring workflow links permit-driven sampling plans with laboratory and SCADA integration, validation, exceedance alerts, DMR generation and audit trails. For each result, the utility should assign a sequence: validate, confirm as required, notify the responsible owner, investigate the source, evaluate pretreatment or treatment response, and document closure.
For solids, define the destination and acceptance criteria before accepting PFAS-bearing sludge into the handling system. The SFPUC reports that a number of other states have set 20 parts per billion as the PFOA and PFOS threshold in biosolids at which action is required to reduce levels; San Francisco’s levels remain below that threshold. That comparison is site- and jurisdiction-specific. It is not a national biosolids limit, and the applicable state or local requirement must be confirmed for the disposal route.
PFAS should be treated as distributed mass rather than a contaminant moving in a straight line from inlet to outlet. Before specifying a plate and frame filter press for PFAS-bearing sludge handling, confirm the solids stream, dewatering objective, sampling point, destination and analytical acceptance criteria. Conventional treatment or sludge dewatering should not be assumed to remove or destroy PFAS. Where treatment selection is also in scope, compare DAF system for industrial wastewater pretreatment options only against the source-control objective and the resulting solids-handling requirement.
Build an RFQ scope and screen supplier responses

A defensible RFQ should make compliance obligations, technical scope and deliverable ownership comparable across bidders. It should identify the jurisdiction and authority, obligation basis, sampling schedule, matrices, locations, analytes, method, reporting limits, quality controls, data format, reporting deadlines, training, support and acceptance tests.
| Quote line item | Technical scope to specify | Red flags to check before signing |
|---|---|---|
| Monitoring program development | Obligation register, sampling-point map, schedule, chain-of-custody process and responsibility matrix | No controlling document, no named authority or no site-specific sampling basis |
| Field sampling | Documented locations, matrix-specific procedures, containers, preservation and sample handoff | One generic method for all matrices or no training and corrective-action requirements |
| Laboratory analysis | Analyte list, EPA Method 1633 where applicable, reporting limits, qualifiers and matrix-specific QC | Omitted method details, reporting limits, blanks or QC acceptance criteria |
| Data validation and reporting | Electronic data, validation record, audit trail, alert workflow and required regulatory outputs | No validation ownership, incomplete audit trail or undefined deliverable format |
| Industrial-user attribution | Source inventory, screening review, representative sampling plan and pretreatment handoff | Unsupported source attribution or collection of data outside the authorized scope |
| Solids assessment | PFAS-bearing sludge sampling, destination review and treatment or dewatering interface | Monitoring bundled with treatment performance claims or no solids-disposal criteria |
| Management and reporting | Owner assignments, escalation, reporting calendar, audit trail and closure records | Unclear data ownership, duplicate charges or no stated response deadlines |
Assign missing site inputs before issuing the RFQ. Utility compliance staff should provide permit records and renewal dates. Operations staff should provide flow, hydraulic and process information. Laboratory staff should define analytical conditions and acceptance criteria. The industrial pretreatment team should supply source information and candidate-user screening. Keep monitoring and analytical services separate from treatment equipment, sludge testing and source-control engineering so that scope, performance claims and payment remain clear.
Further Reading
Frequently Asked Questions
Is PFAS wastewater monitoring legally required, and which document controls?
Ask the utility compliance staff for the permit, consent decree, agency order or written monitoring program that applies to the utility. Confirm the jurisdiction, receiving authority, identifiers, reporting dates and whether the requirement applies to effluent, industrial users, biosolids or the wastewater system generally. Classify each requirement as verified, proposed or site-specific. Do not apply drinking-water standards to wastewater without written confirmation from the authority.
Where should a utility sample PFAS in its wastewater system?
Select sampling points from the decision purpose. Use influent and effluent samples for treatment-performance questions, permit-designated locations for effluent compliance, and biosolids samples when the disposal route requires them. Add representative industrial-user sampling when source attribution is an objective, using the source inventory and screening data first. An outlet grab sample alone cannot answer all three questions.
What should the laboratory quotation include?
Require a matrix-specific package covering the analyte list, method, containers, preservation, holding time, reporting limits, qualifiers, blanks, quality-control acceptance criteria, corrective actions, chain of custody, validation and complete electronic data. State whether the quotation includes influent, effluent, biosolids, industrial-user samples or a combination. A laboratory that does not identify its method-specific reporting limits and QC rules has not supplied a comparable quotation.
What should happen after a PFAS exceedance is confirmed?
Issue a written response procedure before award. It should route the result through validation, required confirmation, notification, source investigation, pretreatment or treatment evaluation, and documented closure. For solids, predefine the destination and applicable acceptance criteria. If treatment or source-control engineering is needed, scope it separately from monitoring and request a wastewater treatment plant cost and quotation scope based on the confirmed analytes, matrices, flows and operating conditions.