Define the greywater project boundary first
The primary choice for a commercial greywater recycling system in Brazil is between ultrafiltration (UF), membrane bioreactors (MBR), or an integrated package treatment plant. UF suits physical separation and polishing of segregated, relatively low-load greywater; MBR adds biological treatment with membrane separation; a package plant integrates a broader treatment train. The decision depends on measured flow and quality, non-potable reuse demands, footprint, and local requirements—not the greywater percentage alone. Source segregation and the intended end use must be fixed before equipment is specified.
Start with a process-flow diagram that identifies every incoming stream. Record whether the system receives showers, washbasins, laundry, kitchen activities or other building wastewater, and exclude toilet flows from the greywater balance. A typical household study found that greywater excluding toilet waste represented 50–80% of daily wastewater generation, but this finding is evidence that segregation can materially change the treatment load; it is not a commercial design ratio (Environmental Science and Ecotechnology).
Define the non-potable application before comparing equipment. A Brazilian commercial supplier cited reuse for toilet flushing, cleaning and common areas, while a separate Pernambuco project used filtered greywater for agroforestry irrigation. Those examples establish possible applications, not equivalent treatment specifications. For the proposed building, identify whether reclaimed water must support toilet flushing, washdown, irrigation or another application; whether demand is continuous or intermittent; and whether any public-health restrictions apply.
Use the commercial greywater route-selection method to turn that boundary into measured inputs. The buyer needs peak and average flow in m³/h, hourly and daily demand profiles, source-water characterization, reuse targets, available footprint, installation depth, electrical supply, local compliance information, staffing capability and maintenance access.
Compare the three commercial treatment routes
Selecting the correct route requires matching the treatment effect to measured source conditions, available space, and the specific reuse application.
UF is a membrane filtration step primarily suited to physical separation and polishing; an hollow-fiber ultrafiltration system should not be treated as the complete biological treatment train unless that scope is demonstrated. An MBR membrane bioreactor combines biological treatment with membrane separation. A package plant can integrate treatment, storage and pumping for a broader scope, but the buyer must confirm how it handles the actual greywater stream and installation conditions.
| Discharge route or influent problem | Governing rule or process option | What data settles it |
|---|---|---|
| Segregated, relatively low-load greywater requiring physical separation or polishing | Evaluate UF as a membrane filtration route, with the required pretreatment and disinfection defined separately. | Source-by-source flow and water-quality characterization, solids content, expected cleaning demand and required reuse quality. |
| Organic load requiring biological treatment before membrane separation | Evaluate MBR, specifying biological capacity, membrane duty, solids handling and the relationship between membrane output and reuse demand. | Measured feed characteristics, hourly load profile, required treated-water quality, residual and sludge handling arrangements. |
| Broader treatment scope or constrained above-ground footprint | Evaluate an integrated package plant; confirm whether its treatment scope covers the non-potable application and local installation requirements. | Complete wastewater balance, available footprint and depth, utility connections, access requirements and operator capability. |
| Variable source streams or intermittent reuse demand | Compare storage, equalization and control logic across all three routes before selecting equipment. | Hourly inflow and demand profiles, minimum operating flow, storage strategy and required availability of reclaimed water. |
Do not accept “UF,” “MBR” or “package” as sufficient technical descriptions. Require the supplier to show the treatment train, design basis, pretreatments, storage, pumping, controls and end-use performance. The UF, MBR and package-plant comparison provides a useful technical starting point, but the commercial decision still depends on Brazilian site data and the project jurisdiction.
Use Brazilian evidence without overgeneralizing it

Brazilian evidence supports decentralized reuse as a project concept, but it does not establish one equipment route or a universal commercial design.
A Life Cycle Sustainability Assessment study covered four cases in Brazil and Germany and found water-reuse scenarios outperformed conventional counterparts across environmental, economic and social dimensions, with overall sustainability scores up to 4.8 times higher than baseline equivalents (MDPI). Its greywater system boundary excluded blackwater and urine, and the assessment was not a direct comparison among UF, MBR and package plants.
Financial assumptions also require local confirmation. The cited IPTU Ecológico provision grants a 4% reduction in property tax for buildings equipped with rainwater harvesting or water reuse systems (MDPI). Before including that benefit in the project case, request current written confirmation from the responsible municipality because eligibility and application can depend on the property and prevailing local rules.
The UNDP account of the RAC-SAF project in Pernambuco describes filtered household greywater used to irrigate agroforests of up to 625 square metres, with approximately 60,000 litres of water reused per year (UNDP Adaptation Initiative). This is a locally adapted community system, not a commercial sizing template. Its value is as an example of matching treatment and reuse to local conditions; a commercial project still needs measured hydraulic, contaminant and maintenance data. A broader view of Brazilian implementation context is available in this Brazilian effluent-treatment market overview.
Build the supplier RFQ around measurable scope
An RFQ becomes comparable when every bidder defines the same design basis and supply boundary.
Request peak and average greywater flow in m³/h, hourly and daily demand profiles, source-segregation drawings, water-quality characterization, reuse targets, available footprint, utility requirements and documented local compliance information. Identify the measured records, sampling plan and local authority documents used to establish these inputs.
Require each supplier to state the design flow, applicable feed-water range and treatment train rather than offering an unqualified capacity figure. The quotation should identify included pretreatment, storage, pumping, disinfection, controls, commissioning, training, spare parts and performance testing. It should also allocate responsibility for installation, civil works, residuals, membrane cleaning, backwash, maintenance and regulatory support.
| Quote line item | Technical scope to specify | Red flags to check before signing |
|---|---|---|
| Design basis and equipment capacity | State average and peak design flow, operating profile, feed-water range, treatment objectives and simultaneous demand assumptions. | A single nominal capacity without an operating envelope, or equipment selected from total building wastewater rather than segregated greywater. |
| Treatment train and reuse performance | List every treatment stage, intended reuse application, pretreatment, disinfection and project-specific acceptance tests. | Generic “suitable for reuse” language without a defined end use, test protocol or evidence from comparable feed water. |
| Civil works, storage and utilities | Define tank volume, installation depth, access, pumping, electrical demand, controls and boundary between supplier and civil contractor. | Unclear foundations, excavation, buried-component access, power assumptions or exclusions that shift cost and risk after award. |
| Residuals and maintenance | Specify membrane cleaning, backwash, sludge or residue handling, operator access, maintenance schedule and spare-parts supply. | No documented route for residuals, no access provision for membrane work, or a maintenance scope requiring unavailable specialist labour. |
| Compliance and handover | Identify applicable local approvals, FAT and SAT responsibilities, training, documentation and corrective-work ownership. | External certification or generic references used in place of project jurisdiction requirements, with acceptance obligations left undefined. |
Evaluate quotations on the same technical scope. Treat external certification claims and generic reuse language as supporting information only; they do not replace verification of local requirements and project-specific acceptance criteria.
Set acceptance criteria before commercial award

Define what “complete and working” means before signature.
Measured acceptance criteria should address throughput, treated-water quality for the agreed non-potable use, automation, leakage, odour and reuse availability. The available evidence does not establish universal regulatory limits for the project jurisdiction, so the owner and local civil engineer must obtain the applicable discharge, reuse and public-health requirements.
Include a factory acceptance test and site acceptance test with documented procedures, calibrated instruments, agreed feed-water and operating conditions, pass/fail criteria and responsibility for corrective work. Require operator training, maintenance access and clear handover documentation before acceptance.
Address variable source conditions, membrane cleaning, backwash, sludge or residue handling and spare-parts support explicitly. Ask for lifecycle documentation covering routine maintenance, membrane replacement intervals, operating controls and troubleshooting. The UF and MBR equipment descriptions identify automatic backwash and air-scour features; the contract should establish how those functions will be demonstrated and maintained rather than leaving them as unqualified product features.
Obtain site data from the building owner and measured greywater records, local compliance confirmation from a civil engineer and the environmental authority, and technical responses from qualified treatment suppliers. The final equipment decision should follow the measured design basis, verified local requirements and agreed acceptance tests.
Frequently Asked Questions
What inputs are needed to size a commercial greywater recycling system in Brazil?
Request peak and average flow in m³/h, hourly and daily demand profiles, source-segregation points, a source-water characterization, the intended non-potable application, available footprint and depth, electrical supply, treatment objectives, staffing and maintenance access. The 50–80% household greywater share reported by Environmental Science and Ecotechnology must not be used as a commercial sizing ratio. Equipment sizing should follow the project’s measured flow, quality and reuse-demand data.
Should the project select UF, MBR or a package treatment plant?
Select UF when measured conditions support physical separation and polishing as the required treatment effect; evaluate MBR where biological treatment and membrane separation are required; and evaluate a package plant where an integrated treatment scope fits the site and installation conditions. Ask each supplier for the complete train and applicable feed-water range. The project’s non-potable end use, hydraulic profile and local requirements determine which route is defensible.
How should performance acceptance be tested?
Define measured throughput, treated-water quality, automation, leakage, odour and reuse-availability criteria before award, then require FAT and SAT with documented procedures and calibrated instruments. Do not import universal thresholds from another jurisdiction or rely on a generic certification claim. The owner should obtain applicable local requirements from a civil engineer and the environmental authority, then make those conditions part of the acceptance schedule.
How should cost and supplier selection be evaluated?
Ask for an itemized quotation covering the design basis, treatment train, civil interfaces, storage, pumping, controls, utilities, commissioning, training, maintenance, residuals and performance testing. Compare bids only after confirming that inclusions and exclusions are equivalent. No project quotation can be responsibly estimated without the measured flow, quality profile, reuse demand, site constraints and local scope; request those inputs from the owner before comparing supplier prices.