Separate the wastewater streams before selecting equipment
A Koto data center should select treatment based on the final use or discharge route rather than a generic template. Cooling blowdown carries concentrated dissolved solids, treatment chemicals, suspended solids, and biocides, while sanitary wastewater requires biological treatment and disinfection. For sewer discharge, the preliminary train includes screening or filtration, clarification, and compliance monitoring; for cooling-makeup reuse, add membrane polishing and disinfection. A 2026 life-cycle analysis found reclaimed-water treatment had about twice the global warming potential of the freshwater case, with treatment energy responsible for roughly 80% of the difference. Koto-specific limits, receiving-water rules, and makeup-water chemistry must be confirmed with the competent authorities before equipment sizing.
KETOS reports that 75–90% of data centers worldwide use water-based cooling, but the site configuration determines the wastewater balance. An open evaporative system typically loses 70–80% of withdrawn water through evaporation and sends 20–30% out as liquid blowdown; a closed-loop or hybrid system consumes 5–10% and returns approximately 90–95% as wastewater (KETOS, 2025). These figures are global system-level benchmarks, not Koto design values. They provide the first split in the data-center water balance, but metered Koto flows must establish the actual duty.
| Stream to segregate | Required metered information | Why it affects treatment selection |
|---|---|---|
| Cooling tower blowdown | Hourly and daily flow; cooling configuration; makeup, evaporation and operational dumps | Determines hydraulic loading, cycles of concentration and concentrate chemistry |
| Sanitary wastewater | Hourly and daily flow; occupancy and operating schedule | Sets biological and disinfection requirements independently of blowdown |
| Process, rainwater, laboratory and battery-room drains | Individual flow and chemistry; isolation status | Prevents incompatible contamination of a common treatment train |
| Combined site discharge | Maximum flow, peak factors, retained volume and permitted discharge points | Controls the selected endpoint and ultimate treatment capacity |
Choose the discharge or reuse endpoint
The end-of-pipe route determines upstream unit operations and chemistry selection. Start by identifying the receiving authority and confirming whether the site will discharge to sewer, discharge directly to a receiving water, reuse water onsite, or use a combination. The Kyoto treatment article describes this decision principle, but its municipal rules, reuse values, and receiving waters do not establish Koto requirements.
| Decision | Confirm before equipment selection | Preliminary treatment implication |
|---|---|---|
| Sewer discharge | Koto sewer authority’s current pretreatment limits for pH, suspended solids, metals, temperature and additive residues | Filtration or clarification; chemical control; residual management; compliance monitoring |
| Direct environmental discharge | Receiving water, applicable national and local water-quality requirements, and thermal-discharge constraints | Broader contaminant removal and potentially greater energy demand; thermal and chemical constraints must be resolved first |
| Onsite low-grade reuse | Internal standard for toilet flushing, irrigation or other selected demand, including public-health requirements | Filtration and disinfection sufficient for the designated use |
| Cooling-tower makeup reuse | Makeup-water chemistry, membrane-fouling risks, required purity and compatibility with the cooling program | Multi-media filtration, softening where required, industrial reverse osmosis and final disinfection |
For sewer discharge, do not transfer Kyoto or Kyoto-fu limits into the Koto design basis. Request the competent Koto sewer authority’s current pretreatment rules and identify whether cooling additives require specific limits, monitoring, or reporting. For direct discharge, establish the receiving water and thermal constraints before selecting clarification, biological, or membrane processes.
Onsite reuse should be cascaded by quality demand. The Kyoto article places toilet flushing or irrigation below cooling-tower makeup because the latter requires more stringent dissolved-solids control and tighter fouling protection. That hierarchy is engineering logic, not confirmation of Koto rules. Each reuse destination needs its own quality specification and approval route, while residual purge remains a separately permitted discharge stream.
Characterize contaminants that control the treatment train

Cooling-blowdown chemistry is determined by the concentration and composition of the circulating water, not by the nameplate cooling capacity. The Kyoto comparison gives the blowdown-to-makeup relationship as 1 divided by CoC minus 1: at 4 CoC, blowdown is 25% of makeup; at 6 CoC, it is 20% (Genesis Water Technologies, 2025). Increasing cycles of concentration reduces discharge volume while increasing the concentration of dissolved additives and contaminants.
| Parameter to obtain | Design role | Sampling or control requirement |
|---|---|---|
| Conductivity or TDS; pH; temperature | Quantify concentration, corrosion exposure and blowdown control | Continuous makeup, blowdown and recirculating-loop monitoring |
| TSS and settleable solids | Sets filtration, clarification and sludge-handling duty | Representative samples across operating conditions |
| Hardness and silica | Identifies scaling and RO-fouling constraints | Analyze makeup and blowdown, including seasonal variation |
| Chloride and metals in the cooling program | Defines discharge and reuse limits | Include metals actually dosed or expected through corrosion |
| Residual oxidant, biocide and corrosion-inhibitor residues | Controls disinfection, membrane compatibility and permit compliance | Document products, dosage and residual after the cooling tower |
| Phosphorus where applicable | Assesses nutrient or permit implications | Tie sampling to the chemical program |
Suspended solids can originate from airborne dust, scale flakes, and microbiological growth, while an aggressive biocide or corrosion-inhibitor program can increase the dissolved-solids load (Genesis Water Technologies, 2025). Sample the actual water rather than relying on chemical inventory alone: concentration and treatment history determine the composition of the discharge.
Install conductivity, pH, and temperature monitoring at makeup, blowdown, and the recirculating loop. The Kyoto comparison reports that actual blowdown can exceed theoretical calculations by 15–30% because of unmeasured losses and emergency dumps (Genesis Water Technologies, 2025). Equipment sizing should therefore use measured operating data and explicitly included upset conditions, not only the steady-state water balance.
Match unit operations to the selected endpoint
Physical pretreatment comes first for solids-bearing blowdown because clarification and membranes cannot be specified reliably without a solids load. The Kyoto treatment sequence starts with side-stream filtration, followed by lamella clarification or DAF equipment for cooling-blowdown solids removal when suspended solids, oil, or floc make clarification necessary. The cooling blowdown treatment guide provides a parallel humid-site reference, but its requirements and equipment assumptions must not be transferred to Koto.
| Selected endpoint | Indicative preliminary train | Acceptance focus |
|---|---|---|
| Sewer discharge | Screen or filter; clarification if solids justify it; pH and additive residual control; monitoring | Confirmed Koto limits at the point of discharge |
| Sanitary wastewater | Equalization; biological treatment; sedimentation; disinfection | Hydraulic and organic loading with the required sanitary outlet quality |
| Low-grade onsite reuse | Filtration; disinfection; storage and distribution controls | The quality specification for the selected reuse demand |
| Cooling-tower makeup reuse | Multi-media filtration; industrial softening where required; industrial reverse osmosis; disinfection | Makeup chemistry, fouling control, scaling protection and system compatibility |
For high-grade cooling makeup, multi-media filtration and industrial reverse osmosis are the Kyoto article’s logical sequence, with industrial softening where required. The 2026 comparative LCA found UF plus RO energy usage above five times the freshwater case, partly balanced by improved cycles of concentration that reduce blowdown and chemical consumption (Open Engineering Inc, 2026). The same study found the wastewater scenario had about twice the freshwater case’s GWP and that treatment energy accounted for roughly 80% of the difference. These findings make recovery, energy, and operating cost explicit procurement variables.
For microbial control, the Kyoto comparison identifies chlorine dioxide as an option. Verify the residual limit, oxidant demand, contact arrangement, and material compatibility for the selected Koto route before including it. A dosing skid should also define chemical storage, containment, interlocks, alarms, and the consequences of overfeed.
Build the pre-design data request and acceptance criteria

A procurement package should force vendors to select equipment from measured site duties and a confirmed legal endpoint. Request 12 months of makeup, blowdown, and wastewater flow data where available, together with proposed cooling configuration, IT load, operating profile, design cycles of concentration, and seasonal control strategy. If the operating history is incomplete, require a metered baseline study rather than accepting nominal water use as a substitute.
| Information package | Required content | Why it belongs in the bid |
|---|---|---|
| Site water balance | Separate hourly and daily flows for each stream; maximum and minimum flows; future expansion | Defines hydraulic loading and storage requirements |
| Water characterization | Makeup and blowdown analyses across operating conditions; complete chemical program | Defines clarification, membrane, corrosion and residual-control duties |
| Regulatory route | Current Koto authority limits, receiving-water constraints, reuse standard and residual-purge route | Prevents an equipment package based on an unresolved endpoint |
| Guaranteed performance | Guaranteed inlet and outlet flow, TSS, conductivity or TDS and relevant chemical-residue duties | Creates a comparable technical basis for acceptance |
| Execution | Controls, alarms, PLC or BMS integration, commissioning tests and validation responsibilities | Allocates operational and compliance risk |
| Lifecycle support | Membrane and media availability, spare-part support, consumables, cleaning and maintenance access | Supports reliable operation after handover |
Issue the permit route and supporting authority documents to bidders. Any proposed route that depends on an unconfirmed Koto limit should remain explicitly conditional. Require vendors to identify which guarantees depend on that unresolved condition and which performance can be demonstrated independently.
Evaluate alarm response, control interlocks, and BMS or PLC integration against the site operating philosophy. Require local spare-part and consumables support for Kansai-region operations, together with documented membrane and media availability. The data-center wastewater commissioning guide can inform the commissioning checklist, but Koto acceptance criteria must follow the confirmed authority route and site data.
Frequently Asked Questions
How should treatment equipment be sized for a Koto data center?
Size each train from separate measured flows and water analyses for cooling blowdown, sanitary wastewater, and other drains, then apply the selected endpoint’s confirmed quality duties. Include seasonal peaks, emergency dumps, future expansion, and the measured deviation between theoretical and actual blowdown; do not size from IT load or total water withdrawal alone.
How should vendors be selected without a confirmed Koto discharge permit?
Require a base bid based on the intended endpoint plus a clearly priced alternative for each unresolved route. Assess guaranteed inlet and outlet duties, controls integration, commissioning validation, local spare-part support, and membrane or media availability. Treat Kyoto limits as reference material, not Koto acceptance criteria, until the competent authority confirms the applicable requirements.
What inputs are needed for a treatment-cost comparison?
Ask each bidder for a transparent comparison of capital equipment, installation, utilities, chemicals, media and membrane replacement, waste disposal, labor, and expected energy use. Also request the site inputs needed to complete the comparison: flow profiles, analyses, selected endpoint, cooling configuration, reuse fraction, and operating schedule. A defensible quotation should state exclusions and assumptions rather than provide an unsupported total price.
Should sanitary wastewater and cooling blowdown be treated together?
Not until their flows, contaminants, and legal routes are documented. Cooling blowdown is concentrated by evaporation and contains treatment-chemical residues, while sanitary wastewater requires a biological treatment and disinfection basis. Segregate the streams through characterization and endpoint review; combine them only if the authority approves the route and the preliminary treatment design demonstrates compatible loading and effluent quality.