MABR Retrofit of Existing Infrastructure: Windsor, California 2026

If your plant has to remove more nitrogen and phosphorus on a site that has no room to grow, MABR (membrane aerated biofilm reactor) modules are one retrofit route for existing infrastructure that is worth putting on the shortlist. The reference case is Windsor, California: on 2026-11-17 DuPont announced that its OxyMem™ MABR modules have been selected for an upgrade to the Windsor Water Reclamation Facility. In DuPont's account the project addresses three constraints at once: the site is space-constrained, the plant must keep complying with stringent nitrogen and phosphorus discharge limits, and the town wants to decarbonize its biological nutrient removal (BNR) system while adding treatment capacity in stages. The announcement carries no design data, so treat it as a starting point: before a similar project is approved, the owner, the designer and the supplier each have items to confirm.

The event facts in this article come from one document: DuPont's press release of 2026-11-17 (first paragraph: modules selected for an upgrade to the Windsor Water Reclamation Facility; second paragraph: design partners and purpose of the project; third paragraph: the vendor's description of its modules). It is a supplier announcement, not a notice from the Town of Windsor, which operates the plant. DuPont calls the project the first municipal deployment of OxyMem™ MABR modules in the United States and says it was designed in collaboration with Black and Veatch, MISCOwater and United Flow Technologies.

What the Windsor release says, and what it leaves out

The release is short and qualitative. The table separates what it states from what remains open; the data it does not disclose are listed in the FAQ below.

Check itemWhat the release saysTo confirm before approval
SiteThe town operates a space-constrained siteUsable space and hydraulic conditions in the existing facilities
TargetsStringent nitrogen and phosphorus limitsInfluent loads and effluent targets, from the owner
CapacityModular design aligned with adaptive planning; capacity added incrementallyModule count and size; interfaces for later phases
Energy and carbonDuPont: modules designed to lower aeration energy demandEnergy baseline and the method for verifying any change
PhaseSelected for an upgrade (2026-11-17)Installation, commissioning and acceptance timing

Two statements in the release are the vendor's description of its product, not results from Windsor. DuPont says the modules are designed to give drop-in process intensification, increasing nutrient removal capacity within existing infrastructure while reducing the energy needed for biological treatment, and that their oxygen transfer process can lower aeration energy demand. Steve Ebersohl, Americas Commercial Leader at DuPont Water Solutions, frames this as a need for utilities to do more with the infrastructure they already have. None of it is a measured outcome at Windsor or a value you can put into a design basis; ask a supplier to turn each claim into a guaranteed figure and a test method for your own plant.

Checklist before selecting an MABR retrofit

The list below is our suggested preparation for a retrofit of this kind. It is not a requirement published by the Town of Windsor or by DuPont, and it is not bid or legal advice; it is what we would expect on the table before a selection is made, grouped by the party who should supply each item.

At project initiation: the owner

  • The design basis: present and future flows, incoming nitrogen and phosphorus loads, and the effluent targets the upgrade has to reach. The release publishes none of these for Windsor; they come from the owner's records and discharge permit.
  • The space that can genuinely be spared inside the existing facilities, with access for lifting and maintenance, and the hydraulic head available across it.
  • An energy baseline with a stated metering method, so that aeration energy can be compared on the same basis before and after the retrofit.
  • Which process trains may be taken out of service, and for how long, while the plant stays within its discharge limits.

At quotation: the supplier

  • The number, size and arrangement of modules offered, and the interfaces that let a later phase be added without redoing the first.
  • Air supply: the air flow and pressure the modules need, the blowers proposed to match, and how the supply is controlled.
  • The performance guarantee: what is covered (effluent nutrients, aeration energy or both), the test protocol and its duration, and the operating conditions it assumes.
  • Membrane life: the expected replacement interval, the cleaning routine, and what the warranty does not cover.

At technical verification: owner, designer and supplier together

  • Integration: where each module sits and how flow is split to and collected from it, checked against as-built drawings and a site survey.
  • The installation sequence: tie-ins and bypass arrangements that keep the plant in compliance throughout the works.
  • Commissioning and acceptance: the start-up period allowed for the biofilm, the sampling and metering method, and the pass criteria.

MABR is not MBR

One point of naming causes real confusion in retrofit enquiries. MBR (membrane bioreactor) uses membranes to filter the mixed liquor and retain suspended solids in place of secondary settling. MABR uses membranes for a different job: delivering oxygen to a biofilm that grows on the membrane surface. The two processes are not interchangeable. For comparison, our MBR Membrane Bioreactor Wastewater Treatment System product page shows this site's MBR equipment; it is a reference only, not the equipment selected for the Windsor project, and HydropureWater has no role in that project.

For the process parameters, sizing and aeration calculations behind an MABR selection, see MABR Design Guide 2026: Process Parameters, Sizing & Aeration Calculations. For procurement on the utility side, see MABR for Municipal Sewage: 2026 Engineering Buyer’s Guide. The wider national context is in our Wastewater Treatment in United States country page.

FAQ

What stage has the Windsor MABR project reached?

As of DuPont's announcement of 2026-11-17, the OxyMem MABR modules have been selected for an upgrade to the Windsor Water Reclamation Facility. The release headline and its closing paragraph use the word installation, but the opening paragraph says only that the modules were selected, the subtitle is in the future tense, and the release gives no installation, commissioning or operating results. Any later status should be taken from the Town of Windsor or from DuPont's own updates.

Which key data does the announcement leave out?

It gives no plant flow capacity, no number or size of modules, no description of the structures involved, no construction or commissioning dates, no contract value, and no measured effluent quality or energy savings. Each of these has to be confirmed with the supplier and the designer before it is used in a feasibility study or a business case.

What kind of plant is an MABR retrofit suited to?

The Windsor case offers a profile rather than a rule: a site with little free space, stringent nitrogen and phosphorus limits, energy and decarbonization goals, and capacity that has to be added in stages within the existing site. Whether MABR fits a particular plant is a process design question; start with the design guide linked above and have the designer run the load and aeration calculations.

Are MABR and MBR the same technology?

No. MBR is a membrane filtration process that retains suspended solids and so replaces secondary clarification. MABR is an aeration process in which the membrane feeds oxygen to a biofilm on its surface. The two can be found in the same plant for different reasons, but they are not substitutes, and the MBR product page linked above is not a description of MABR.

References

  1. DuPont announces first OxyMem™ MABR installation in the United States

Related Articles

MABR Design Guide 2026: Process Parameters, Sizing & Aeration Calculations
Sep 28, 2026

MABR Design Guide 2026: Process Parameters, Sizing & Aeration Calculations

MABR design guide 2026 — membrane aeration rates, biofilm kinetics, SRT/HRT, hydraulic sizing, and …

MABR for Municipal Sewage: 2026 Engineering Buyer’s Guide
Nov 2, 2026

MABR for Municipal Sewage: 2026 Engineering Buyer’s Guide

Compare MABR, activated sludge and MBR for municipal sewage treatment, with process design, nutrien…

AI Growth
Contact
Contact Us
Call Us
+86-181-0655-2851
Email Us Get a Quote Contact Us